# DC2023-06-0019 — Adopting the Guidelines Governing the 4th Open and Competitive Selection Process (OCSP4) in the Award of Renewable Energy Service Contracts

**Department Circular No. DC2023-06-0019**

Signed: 8 June 2023 | Secretary Raphael P.M. Lotilla
Effectivity: 15 days after publication in at least two (2) newspapers of general circulation; copy filed with UP Law Center-ONAR

Legal basis: RA 7638 (DOE Act of 1992); RA 9513 (RE Act of 2008); DC2022-11-0034 (IRR amendment on RE Service Contract eligibility); DC2019-10-0013 (Omnibus RE Contract Guidelines) §13 (OCSP procedures)

PDAs covered: 3 geothermal, 14 hydropower, 3 wind — 20 Pre-Determined Areas total

---

## MAIN CIRCULAR

### Section 1. Scope of Coverage

The Guidelines adopted under this Circular shall govern the determination of the legal, financial and technical qualifications of RE Applicants, the evaluation of their Applications, and the award of RE Contracts.

### Section 2. Review and Evaluation Committee (REC)

The REC is hereby created to carry out the duties and responsibilities set forth in this Circular.

**Composition:**
| Role | Position |
|------|---------|
| Chairperson | Supervising Assistant Secretary, REMB |
| Vice-Chairperson | Director, REMB |
| Member | Chief, Geothermal Energy Management Division (GEMD) |
| Member | Chief, Hydropower and Ocean Energy Management Division (HOEMD) |
| Member | Chief, Solar and Wind Energy Management Division (SWEMD) |
| Member | Chief, Renewable Energy Legal Services Division (RELSD) |
| Member | Chief, Renewable Energy Resources Compliance Division (RERCD) |
| Secretariat | Staff of GEMD, HOEMD, and SWEMD |

### Section 3. Duties and Responsibilities of the REC

- 3.1 Examine and evaluate completeness of applications and legal, technical, and financial qualifications of RE Applicants;
- 3.2 Resolve any objections raised by RE Applicants on findings, including Motions for Reconsideration, or other issues in the conduct of the OCSP;
- 3.3 Recommend to the Secretary the award of a Renewable Energy Service Contract (RESC) in favor of the RE Applicant with the highest rank, or to the sole qualified RE Applicant;
- 3.4 Address questions raised by the Secretary in connection with any endorsement to award RESCs; and
- 3.5 Other functions as may be delegated by the Secretary.

### Section 4. Lead Unit

DOE-REMB shall be the lead unit in the implementation of this Circular.

### Section 5. Separability Clause

### Section 6. Repealing Clause

### Section 7. Effectivity

This Circular shall take into effect fifteen (15) days following its publication in at least two (2) newspapers of general circulation. A copy shall be filed with UP Law Center-ONAR.

---

## GUIDELINES GOVERNING THE 4TH OPEN AND COMPETITIVE SELECTION PROCESS (OCSP4) IN THE AWARD OF RENEWABLE ENERGY (RE) SERVICE CONTRACTS

---

## WHO MAY APPLY

### 1. Eligibility Criteria for RE Applicants

In accordance with the exceptions provided under DC2022-11-0034:

**1.1** RE Applicant may be a Filipino and/or foreign citizen, or a Filipino- and/or foreign-owned corporation or association authorized to engage in RE exploration, development, and utilization.

**1.2** Appropriation of water directly from a natural source (PD 1067; IDEALS v. PSALM G.R. No. 192088, 09 October 2012) is reserved to Filipino citizens or corporations or associations with at least **60%** Filipino capital.

**Geothermal exception (GSC):** RE Applicant for a Geothermal Service Contract (GSC) must be Filipino or a corporation with at least 60% Filipino capitalization, registered with SEC. However, foreign-owned corporations may also participate, **Provided** the GSC shall be in the nature of a Financial or Technical Assistance Agreement (FTAA) signed by the President, involving technical or financial assistance for large-scale exploration, development, and utilization of geothermal resources under the Philippine Constitution Art. XII §2. **Large-scale geothermal** = project with an initial investment of at least **US$ 50 Million** (includes capitalization during Pre-Development stage up to drilling of appropriate number of production wells).

**Joint ventures/consortiums:** Must organize as a corporation under the Revised Corporation Code of the Philippines, or secure appropriate license from SEC if incorporated outside the Philippines. Joint ventures/consortiums applying for contracts involving activities reserved to Filipinos shall comply with the 60% Filipino capital requirement and the Anti-Dummy Law (CA 108), except for GSC-FTAA applications.

---

## PRE-OCSP ACTIVITIES

### 2. Procedure for the Conduct of the OCSP

**2.1 Launch and Publication** — Invitation to prospective RE Applicants shall be published at least once a week for two (2) consecutive weeks in at least two (2) newspapers of general circulation and posted on the DOE website.

**2.2 Pre-Submission Conference:**
- 2.2.1 Held on date and venue set by REMB; attendance is optional;
- 2.2.2 Statements made at the conference shall not modify or amend OCSP terms unless adopted as a Supplemental OCSP Bulletin; and
- 2.2.3 Supplemental OCSP Bulletin (if any) posted on DOE website within **7 working days** from the conduct of the Pre-Submission Conference.

### 3. RE Contract Application

**3.1** RE Application submission period: Beginning the day immediately following the publication date, until the **last day of submission (60 calendar days from the date of first publication)**. Requirements:
- 3.1.1 Letter of Intent (LOI) per Annex A format, with documentary requirements (Annex B);
- 3.1.2 Each RE Application shall cover only one PDA;
- 3.1.3 Submission in both paper and electronic (PDF in flash drive) copies; Times New Roman 12pt single-spaced, A4; figures/maps in A3 or larger at 1:50,000 scale;
- 3.1.4 **Non-refundable application fees** (proof of payment required for data access):

| Resource Type | Application Fee |
|---------------|-----------------|
| Hydropower <50 MW | PhP 50,000 per project |
| Hydropower ≥50 MW | PhP 100,000 per project |
| Geothermal | PhP 20,000 per project + total amount of data access from EDCP |
| Wind | PhP 100,000 per project |

Accepted payment modes: Cash, manager/company check (payable to "Department of Energy"); over-the-counter at DOE Treasury Division; Online Bank Transfer/Wire Transfer/Telegraphic Transfer (net of bank charges).

**DOE Trust Fund Bank Details:**
- Account Number: 0052-1155-58
- Bank: Land Bank of the Philippines — Buendia Branch

3.1.5 Data access procedure (for those who paid the application fee):
- Submit LOI via email to: `remb9513@doe.gov.ph`; `geothermaldivision@gmail.com` (Geothermal); `doe.remb.hoemd@gmail.com` (Hydropower); `swemd.remb@doe.gov.ph` (Wind)
- After LOI submission, receive: Order of payment for application fee; Pre-approved data request form; Transmittal/Data Use Agreement
- Send signed documents + official receipt to EDCP via `edcp@doe.gov.ph`
- EDCP sends download link containing: Technical data; Technical description of PDAs; Copy of OCSP4 Guidelines

### 4. Filing Process

4.1–4.2 RE Applicants shall submit 3 sets of documentary requirements (1 original + 2 photocopies) in 3 sealed envelopes:
- **Envelope A:** Legal documents
- **Envelope B:** Financial documents (includes Annex D financial commitment summary)
- **Envelope C:** Technical documents (includes Work Program Annex E and Track Records Annex F)

4.3 Improperly sealed envelopes: DOE assumes no responsibility for misplacement or premature opening.

4.6 Filing may be personal, by registered mail, or private courier; addressed to: REMB Assistant Secretary, DOE, Energy Center, Rizal Drive, Bonifacio Global City, Taguig City, 1632.

4.8 Applications received after deadline shall not be accepted.

4.9 RMD receives applications only during office hours (0800–1700H).

4.10 Representatives of RMD and REMB shall affix signatures on the envelope/container upon receipt.

### 5. Modification and Withdrawal of Applications

5.1 Modification allowed only once; must be received by REMB on or before the submission deadline. Original Application is automatically disregarded upon timely receipt of the modified Application.

5.2 Withdrawal in writing prior to the submission deadline; Application returned unopened.

5.3 RE Applicant that withdraws is not permitted to submit another Application, directly or indirectly, for the same project.

---

## OCSP PROPER

### 6. Opening, Evaluation, Selection, and Award of RE Applications

6.1 DOE stops receiving Applications at **1200H on the last day** of submission. Opening of Applications begins at **1300H**.

6.2 REC opens Applications in public to determine completeness. Envelopes A, B, and C opened simultaneously; REC determines completeness against the checklist (Annex B). Only complete Applications shall undergo legal, technical, and financial evaluation.

6.3 Incomplete Applications automatically disqualified at opening. No additional documents accepted after the deadline. For incomplete hard copy submissions, application is automatically disqualified.

6.4 **Processing fees** (for those that passed the completeness check, paid within 3 calendar days from receipt of Order of Payment):

| Resource Type | Processing Fee |
|---------------|----------------|
| Hydropower | PhP 23,850 per project |
| Geothermal | PhP 8.20 per hectare |
| Wind | PhP 6.50 per hectare |

6.5 RE Applications that passed the completeness check shall be evaluated simultaneously based on the criteria in Annex G:

| Criterion | Key Elements | Weight |
|-----------|-------------|--------|
| Legal Documentation | Legal documents | Pass/Fail |
| Work Program | Literature review; resource exploration strategies and methodologies | 40% |
| Technical Qualifications | Company performance; key management and technical personnel qualifications; technical resources | 20% |
| Financial Qualifications | Available working capital; sources of current funds; other sources of future funds | 40% |

6.6 REC shall complete evaluation within **10 working days** from the date of opening of Applications.

6.7 Highest ranked RE Application meeting all requirements shall be selected. In case of a tie, the winner shall be decided by a **coin toss** in the presence of both parties.

6.8 RE Application failing to obtain the **minimum point requirement per criterion** shall not qualify even if it is the sole participant for the project/site.

6.9 After complete review and evaluation, REC shall transmit a written endorsement of the selected RE Application to the DOE Secretary.

6.10 DOE Secretary may approve the results of evaluation and preparation for the issuance of the corresponding RE Contract.

6.11 Upon approval by the Secretary, results of OCSP4 shall be posted on the DOE website.

### 7. Failure of OCSP

The OCSP shall be declared a **failure** for any or all PDAs when:

7.1 No RE Application was received within the allotted period;
7.2 No RE Application passed the legal requirements; or
7.3 One or more RE Applications passed the legal requirements, but after evaluation of technical and financial proposals, none met either the technical or financial requirements.

In any of the foregoing cases, the **PDA shall be opened for Direct Applications**. DOE shall include in the announcement of OCSP results the area(s) that shall be open for Direct Application, indicating when the new application process shall commence.

### 8. Timeline

Timeline for OCSP4 and awarding of RE Contracts (per Annex I):

| Step | Activity | Timeline |
|------|----------|---------|
| 1 | Publication of OCSP4 | Day 1 |
| 2 | Launching and Pre-Submission Conference | Day 1 + 20 CD |
| 3 | Submission of bid documents | Day 1 + 60 CD (on or before, 1200H) |
| 4 | Opening of bid documents | Day 1 + 60 CD (at 1300H) |
| 5 | Complete legal, technical, and financial evaluation | Day 61 + 10 WD |
| 6 | Endorsement of results for concurrence of ASec | — |
| 7 | Approval by the Secretary | Day 76 + 5 WD |
| 8 | Pre-signing of RE Contract and endorsement to Secretary | Day 81 + 19 WD |
| 9 | Signature of the Secretary / Awarding of RE Contract | Day 28 |

For FTAA Applications, activities 1–8 are the same. Activity 10: Endorsement of the Secretary to the Office of the President.

CD = Calendar Days; WD = Working Days.

---

## PRE-DETERMINED AREAS (PDAS) FOR OCSP4

### Geothermal Energy Resources (3 Projects)

| No. | Project Name | Location | Estimated Capacity |
|-----|-------------|----------|-------------------|
| 1 | Buguias-Tinoc Geothermal Project (High Temperature System) | Tinoc, Ifugao | 100 MW |
| 2 | Mabini Geothermal Project (Intermediate Temperature System) | — | 40 MW |
| 3 | Mt. Sembrano Geothermal Project (Low to Intermediate Temperature System) | Pililla and Jala-jala, Rizal; Pangil and Pakil, Laguna | 20 MW |

*Note: Geothermal potential capacities are estimated from P50 results of Monte Carlo simulation.*

### Hydropower Energy Resources (14 Projects)

| No. | Project Name | Location | Estimated Capacity |
|-----|-------------|----------|-------------------|
| 1 | Tinoc 4 Hydroelectric Power Project | Tinoc, Ifugao | — |
| 2 | Alilem Hydroelectric Power Project | Alilem, Ilocos Sur | 16.2 MW |
| 3 | Sibalom (Upper) Hydroelectric Power Project | San Remigio, Antique | 5.0 MW |
| 4 | Main Aklan Hydroelectric Power Project | Libacao, Aklan | — |
| 5 | Basak II Hydroelectric Power Project | Badian, Cebu | 0.5 MW |
| 6 | Sawaga Hydroelectric Power Project | Malaybalay, Bukidnon | 4.5 MW |
| 7 | Davildavilan River Hydroelectric Power Project | Surigao del Sur | — |
| 8 | Carac-an Hydroelectric Power Project | — | — |
| 9 | Ruparan Hydroelectric Power Project | — | — |
| 10 | Canayan Hydroelectric Power Project | Malaybalay, Bukidnon | 5.65 MW |
| 11 | Three Rivers Hydroelectric Power Project | — | — |
| 12 | Catuiran (Upper Cascade) Hydroelectric Power Project | Occidental Mindoro | 3.6 MW |
| 13 | Langaran Hydroelectric Power Project | — | — |
| 14 | Baua Hydroelectric Power Project | Gonzaga, Cagayan | 1.71 MW |

### Wind Energy Resources (3 Projects)

| No. | Project Name | Location | Estimated Capacity |
|-----|-------------|----------|-------------------|
| 1 | San Jose Wind Power Project | San Jose City, Nueva Ecija | TBD |
| 2 | Pantabangan Wind Power Project | Pantabangan, Nueva Ecija | TBD |
| 3 | Bagac Wind Power Project | Bagac, Bataan | TBD |

---

## ANNEX A — Letter of Intent Template

Standard LOI format expressing intent to apply for RE Contract for a specified geothermal/hydropower/wind project area. Requires notarized Letter of Authority (for individuals) or Board Resolution (for corporations), if applicable.

---

## ANNEX B — Checklist of Requirements

Three-envelope system. Requirements by category:

**Envelope A — Legal Documents:**
- 1.1 For individuals: Birth Certificate (PSA), current Business Permit, DTI registration (if applicable), SPA to negotiate and enter into RE Contract (if applicable)
- 1.2 For corporations/JV/consortium: SEC-certified By-Laws and Articles of Incorporation (with corporate stockholders' BL and AOI); Board Resolution; latest General Information Sheet (GIS); certified Business Permit; Organizational Chart; for foreign corporations: documents authenticated by Philippine Consulate or apostilled

**Envelope C — Technical Documents:**
- 2.1 Work Program in Gantt Chart and Narrative Form (Annex E)
- 2.2 Experience/Track Record of the Company (Annex F-1 and F-2)
- 2.3 CVs of key management and technical personnel (Annex F-3, duly notarized)
- 2.4 CVs of technical consultants with corresponding contracts
- 2.5 List of existing company-owned and leased equipment

**Envelope B — Financial Documents:**
- 3.1 Latest Annual Report and/or Audited Financial Statements for last 2 years from filing date, plus latest Unaudited FS if Audited FS is more than 6 months old at time of filing
- 3.2 Bank certification substantiating cash balance
- 3.3 Projected Cash Flow Statement for next 2 years (except geothermal and large hydro: 5 years), showing fund sources and uses, supported by: Sales Agreement/PO of buyer; Sworn Letter of Commitment from stockholders for equity/cash infusion; or Bank-approved loan/credit line
- 3.4 For applicants with insufficient funds: newly organized corporations (≤2 years) must provide parent company's financial documents and Letter of Guaranty; subsidiary corporations (>2 years) must provide either notarized Letter of Guaranty from majority shareholders with bank proof of capacity, or parent company's financial documents and Letter of Guaranty

---

## ANNEX C — Labelling Format for RE Applications

Three sealed envelopes (A, B, C) plus a flash drive of scanned originals. Each envelope must contain: 1 original + 2 photocopies; table of contents with chronological list of documents; each document bearing its appendix number and saved as a separate searchable PDF on the USB.

---

## ANNEX D — Highlights of Contract Terms, Fiscal Incentives and Required Financial Commitments

### D-1 Hydropower Service Contract

| Term | Detail |
|------|--------|
| Pre-Development Stage | 5 years |
| Development Stage | 25 years from effectivity of contract + renewable for not more than 25 years |
| Signature Bonus (one-time) | PhP 5.00/kW |
| Development Assistance (one-time) | PhP 5,000/kW; 1 MW and below exempted |
| Training Assistance (annual, cumulative) | PhP 5.00/kW; 1 MW and below exempted |
| Income Tax | Income Tax Holiday for 7 years |
| Corporate Income Tax | Reduced rate of 10% after ITH |
| Government Share | 1% of gross income |
| Importation | Duty-free importation of equipment, machinery, spare parts, and materials directly used for hydropower operation, for 10 years from registration |

### D-2 Geothermal Service Contract

| Term | Detail |
|------|--------|
| Pre-Development Stage | 7 years |
| Development Stage | 25 years from effectivity of contract + renewable for not more than 25 years |
| Signing Fee (one-time) | PhP 100.00 per hectare of contract area |
| Development Assistance — Pre-Dev Stage | PhP 100.00 per hectare |
| Development Assistance — Development Stage | Minimum PhP 500,000 |
| Training Assistance — Pre-Dev Stage | PhP 100.00 per hectare per year, cumulative |
| Training Assistance — Development Stage | Minimum PhP 500,000 per year, cumulative |
| Income Tax | Income Tax Holiday for 7 years |
| Corporate Income Tax | Reduced rate of 10% after ITH |
| Government Share | 1.5% of gross income |
| Importation | Duty-free importation of equipment, machinery, spare parts, and materials directly used for geothermal power operation, for 10 years |

### D-2 Wind Energy Service Contract

| Term | Detail |
|------|--------|
| Pre-Development Stage | 5 years |
| Development Stage | 25 years from effectivity of contract + renewable for not more than 25 years |
| Signature Bonus (one-time) | PhP 100.00/hectare |
| Development Assistance — Pre-Dev Stage | PhP 100.00 per hectare |
| Development Assistance — Development Stage | PhP 600.00 per hectare or PhP 50,000, whichever is higher |
| Training Assistance — Pre-Dev Stage | PhP 100.00 per hectare per contract year |
| Training Assistance — Development Stage | PhP 300.00 per hectare or PhP 50,000, whichever is higher |
| Income Tax | Income Tax Holiday for 7 years |
| Corporate Income Tax | Reduced rate of 10% after ITH |
| Government Share | 1% of gross income |
| Importation | Duty-free importation of equipment, machinery, spare parts, and materials directly used for wind power operation, for 10 years |

---

## ANNEX E — Work Programs

### E-1 Work Program for Geothermal Energy Projects (Pre-Development: 7 years)

Minimum activities:

1. Secure permits and licenses: Stakeholders consultation; CP or CNO from NCIP; CNC from DENR (surface studies including slimhole drilling); ECC for conventional drilling and construction; FLAg/SLUP or SAPA (if applicable); Grid System Impact Study and Interconnection Agreement (TRANSCO/NGCP); Energy Sales Agreement.

2. Sub-Phase 1 — Geoscientific Studies: Reconnaissance survey; review/evaluation of existing data; detailed surface exploration (geological, geochemical, geophysical surveys); resource assessment study.

3. Sub-Phase 2 — Test Drilling Phase: Drilling works preparation; drilling infrastructure construction; detailed EIS; confirmatory/workover drilling; well testing and bore output measurements; conceptual modelling.

4. Sub-Phase 3 — Delineation and Declaration of Commerciality (DOC): Delineation drilling/workover; well testing and bore output measurements; Grid System Impact Study; Feasibility Study and Final EIA; Financial Closing; Declaration of Commerciality.

### E-2 Work Program for Hydropower Projects (Pre-Development: 5 years)

For Pre-Development Stage: Secure permits (LGU, NCIP CNO/CP, DENR ECC, NWRB water rights); Comprehensive Feasibility Study (hydrological/flood, topographic, geological, civil/EME/electrical design, financial, socio-environmental, and market studies); Detailed Engineering Design (geotechnical, hydrological, survey of access road and transmission route, EME/electrical quotation and detailed design, final scheme of development, detailed cost estimate).

For Development Stage: Pre-construction (remaining permits/clearances, review of FS, finalization of detailed engineering design); Construction, Testing, Commissioning, Operation, and Maintenance (detailed construction and commissioning timeline; O&M including flood control, watershed protection, CSR).

### E-3 Work Program for Wind Projects (Pre-Development: 5 years)

For Pre-Development Stage: Feasibility Study (market study, technical impact study, management study, socio-economic and environmental study, financial study with modelling and financial closing); Declaration of Commerciality/Non-Commerciality.

For Development Stage: Pre-construction (government permits and clearances, EPC/O&M contractor selection); Construction Stage (construction, electromechanical completion, full completion); Post-Construction (project commissioning); Operation and Maintenance (commercial operation).

---

## ANNEX F — Track Records and Personnel

### F-1 Experiences/Track Records

RE Applicant must demonstrate any one of the following (under oath with documentary proof):

1. Power Plant Operator — currently operating a power plant or partner in a consortium/corporation operating a power plant; or an Affiliate is the operator and the RE Applicant has entered into an agreement with such Affiliate.

2. Holder of a Renewable Energy Contract — currently holds a RE Service Contract in good standing with DOE; or an Affiliate holds a valid RE Service Contract and the RE Applicant has entered into an agreement with such Affiliate.

"Affiliate" = person directly or indirectly controlling, or under common control with, or controlled by the RE Applicant. Control = power to direct management and policies of a corporation, partnership, or other association through ownership of majority voting capital stock, interlocking directorate, community of interest, or power to elect majority of the board.

For foreign corporations participating through FTAA: submit equivalent documents authenticated by the Philippine Consulate having appropriate jurisdiction.

### F-2 Company Profile Sheet Format

Company name, country, date established, company background, list of corporate members, key personnel (in-house or sub-contractor), list of on-going/completed similar projects, list of existing company-owned and leased equipment.

### F-3 Curriculum Vitae Format

Standard CV format: proposed position, name, profession, date of birth, years with firm, nationality, professional society memberships, tasks assigned, key qualifications, education, employment record (past 10 years), languages, certification, and commitment statement. Duly notarized with competent evidence of identity.

---

## ANNEX G — Criteria for Evaluation

### Overall Criteria

| Criterion | Key Elements | Weight |
|-----------|-------------|--------|
| Legal Documentation | Legal documents | Pass/Fail |
| Work Program | Literature review; resource exploration strategies and methodologies | 40% |
| Technical Qualifications | Company performance; key management and technical personnel qualifications; technical resources | 20% |
| Financial Qualifications | Available working capital; sources of current funds; other sources of future funds | 40% |

Weight percentage equivalents: 40% = 40 points; 20% = 20 points.

### G-1 Technical Evaluation Criteria for Geothermal Energy Projects

**Work Program (40 points):** Resource exploration strategies and methodologies (including review and evaluation of Proposed Work Program commitment, and schedule of activities).

**Technical Qualifications (20 points):** Company performance (company profile and records of present undertakings including parent, predecessor, or affiliated company); Qualification of key management and technical personnel (eligibility of corporate members, eligibility and experiences of technical personnel); Technical resources (list of existing company-owned and/or leased equipment). Key personnel required per Annex H organizational chart (with CVs per Annex F-3).

### G-2 Technical Evaluation Criteria for Hydropower Projects

**Work Program (40 points):**
- Hydro Pre-Development Stage: Government clearances and permits acquisition (40 pts); Comprehensive Feasibility Study; Detailed Engineering Design.
- Hydro Development Stage: Government clearances (42 pts); Comprehensive Feasibility Study review and re-evaluation; Detailed Engineering Design finalization; Construction, Testing, Commissioning, O&M.

**Technical Qualifications (20 points; Large Hydro and Run-of-River):** Technical resources (list of equipment); experience and track record of the company (records of present and past experiences, including parent/predecessor/affiliated company, performance track record in hydropower exploration/development/production, organization/staffing); qualifications of key management and technical personnel (professional background, experiences, resume of technical personnel including consultants).

### G-3 Technical Evaluation Criteria for Wind Energy Projects

**Work Program (40 points):**
- Wind Pre-Development Stage: Market Study (supply and demand analysis, energy/power supply contract negotiation, tariff rates; wind data analysis; delineation and land rights); Technical Impact Study (system/distribution study); Management Study (EPC and O&M contractor selection strategy; implementation strategy; partner negotiation); Socio-Economic and Environmental Study (public consultations, LGU resolutions, DENR permits, NCIP, CAAP, site use agreements); Financial Study (financial modelling, financial closing); Declaration of Commerciality (10 pts). Total: 40 pts / Minimum: 22 pts.
- Wind Development Stage: Pre-construction (remaining permits, EPC work schedule, detailed engineering, financial closing); Construction Stage (start of construction, electromechanical completion, full completion); Post-Construction; O&M.

**Technical Qualifications:** Company track record/experience (company profile and past/present undertakings); Qualification of key management and technical personnel (eligibility and experiences of technical personnel and consultants, with corresponding contracts); Technical resources (list of existing company-owned and/or leased equipment, tools, and software).

**Disqualification:** RE Application failing to obtain the minimum point requirement per criterion shall not qualify even if the Applicant is the sole participant for the project/site.

### G-4 Criteria for Financial Evaluation

1. Minimum working capital (Liquid Assets less Current Liabilities) = **100%** of the financial commitment for the **first contract year** of the proposed Work Program/Plan.

2. Liquid Assets = cash, trade accounts receivables, and short-term investments/placements only. Credit line is **not** a Liquid Asset.

3. Available working capital for OCSP application = net of fund requirements from other applied RE areas and existing energy service/operating contracts commitment for the current year.

4. In case of multiple RE Proposals, the RE Proponent should identify the prioritization of its applications.

---

## ANNEX H — Required Key Personnel for Geothermal Energy Projects

Organizational chart with:
- President/Exploration Manager
- Management/Administrative Unit
- Engineering Unit (divided into): Geological Survey Team (Senior Geologist, Junior Geologist, Geologic Aide); Geochemical Survey Team (Senior Geochemist, Junior Geochemist, Geologic Aide); Geophysical Survey Team (Senior Geophysicist, Junior Geophysicist, Survey Technicians — 2)
- Drilling Management (Senior Drilling Engineer, Drilling Engineer — 2, Reservoir Engineer, Drilling Assistant/Drilling Aide)
- Legal Officer/Team
- Accountant
- Administration Officer

Management Personnel (7); Technical Personnel (in-house and/or contractor).

---

## ANNEX I — Timeline for OCSP4 and Awarding of Service Contract

| Step | Activity | Timeline |
|------|----------|---------|
| 1 | Publication of OCSP4 | Day 1 |
| 2 | Launching and Pre-Submission Conference | Day 1 + 20 CD |
| 3 | Submission of bid documents | Day 1 + 60 CD (on or before, 1200H) |
| 4 | Opening of bid documents | Day 1 + 60 CD (at 1300H) |
| 5 | Complete legal, technical, and financial evaluation | Day 61 + 10 WD |
| 6 | Endorsement of results for concurrence of ASec | — |
| 7 | Approval by the Secretary | Day 76 + 5 WD |
| 8 | Pre-signing of RE Contract and endorsement to Secretary | Day 81 + 19 WD |
| 9 | Signature of the Secretary / Awarding of RE Contract | Day 28 |
| 10 (FTAA only) | Endorsement of the Secretary to the Office of the President | — |

CD = Calendar Days; WD = Working Days.