=== dc2022-05-0017-pages-01.ppm === &; Le Republic of the Philippines Rs 3® DEPARTMENT OF ENERGY 2% Ca (Kagawaran ng Enerhiya) DEPARTMENT CIRCULAR NO. _DC2022-Q5-00I7 on RULES AND REGULATIONS TO IMPLEMENT REPUBLIC ACT NO. 11646 (MICROGRID SYSTEMS ACT) WHEREAS, Section 9 of the 1987 Constitution of the Philippines declares as a policy that the State shall promote a just and dynamic social order that will ensure the prosperity and independence of the nation and free the people from poverty through policies that provide adequate social services, promote full employment, a rising standard of living, and an improved quality of life for all; WHEREAS, Section 20 of the 1987 Constitution of the Philippines also provides that the State recognizes the indispensable role of the private sector, encourages private enterprise, and provides incentives to needed investments; WHEREAS, Section 2 (a) and (b) of Republic Act (RA) No. 9136 or the "Electric Power Industry Reform Act (EPIRA)", declares that it is the policy of the State to ensure and accelerate the total electrification of the country; and, to ensure quality, reliability, security, and affordability of the supply of electric power (ii) ensure transparent and reasonable prices of electricity in a regime of free and fair competition and full public accountability; (iii) enhance the inflow of private capital and broaden the ownership base of the power generation, transmission and distribution sectors; {iv) protect the public interest as it is affected by the rates and services of electric utilities and other providers of electric power, and (v) encourage the efficient use of energy and other modalities of demand-side management; WHEREAS, Section 2 (f) and (h) of the EPIRA states that it is also the policy of the State to protect the public interest as it is affected by the rates and services of electric utilities and other providers of electric power; and, to promote the utilization of indigenous and new and renewable energy resources in power generation in order to reduce dependence on imported energy; WHEREAS, on 21 January 2022, Republic Act No. 11646 entitled “An Act Promoting the Use of Microgrid Systems to Accelerate the Total Electrification of Unserved and Underserved Areas Nationwide” also known as “Microgrid Systems Act” (Act) was approved; WHEREAS, Section 26 of Republic Act No. 11646 states that the Department of Energy (DOE) shall issue the implementing rules and regulations of this Act within sixty (60) working days upon its effectivity; WHEREAS, the DOE in compliance with Section 26 of the Act, issued Special Order $02022-02-0004 on 21 February 2022 creating the Technical Working Group (TWG) composed of the Department of Energy, National Power Corporation, National Electrification Administration, National Transmission Corporation, and the Energy Regulatory Commission to formulate the Implementing Rules and Regulations; === dc2022-05-0017-pages-02.ppm === WHEREAS, the DOE together with the TWG conducted a virtual public consultation with the stakeholders to discuss the proposed implementing rules and regulations on 08 April 2022. NOW, THEREFORE, in consideration of the foregoing, the DOE, pursuant to Section 26 of Republic Act No. 11646, in consultation with appropriate government agencies such as the Energy Regulatory Commission (ERC), Nationa! Electrification Administration (NEA), National Power Corporation (NPC), National Transmission Corporation (TRANSCO) and Electric Power Industry Stakeholders, hereby issues, adopts and promulgates the following rules and regulations to implement the provisions of the Act. PART I. General Provisions SECTION 1. Title This Department Circular shall be known as the “Implementing Rules and Regulations (IRR) of Republic Act No. 11646, otherwise known as the “Micro Grid Systems Act” and hereinafter referred to as the “IRR”. SECTION 2. Declaration of Policies It is hereby declared the policy of the State to: 2.1. Pursue sustainable rural development and poverty reduction towards nation building through energy access; 2.2. Accelerate total electrification and ensure the provision of quality, reliable, secure, and affordable supply of electric power in unserved and underserved areas; 2.3. Promote private sector participation in the electrification of unserved and underserved areas; 2.4. Provide a competitive environment and level playing field for different kinds of energy sources with a preference for low-cost, indigenous, renewable, and environment-friendly sources of energy; and, 2.5. Ensure the adoption of a dynamic regulatory environment that allows end users to benefit from technologies and innovations in the electric power industry. SECTION 3. Scope In accordance with Section 3 of the Act, this IRR shall apply to the development of microgrid systems in unserved and underserved areas nationwide. SECTION 4. Definition of Terms As used in the Act and this IRR, the following terms shall be defined as follows: 4.1. Authority to Operate (ATO) refers to the document issued by the Energy Regulatory Commission (ERC) to the microgrid system provider, which shall constitute the latter's license to provide integrated power generation and distribution services to unserved or underserved areas; === dc2022-05-0017-pages-03.ppm === 4.2. Certificate of Compliance (COC) refers to a license issued by the ERC in favor of a person or entity to operate a power plant or other facilities used in the generation of electricity pursuant to Section 6 of RA 9136 and Section 4 of the Implementing Rules and Regulations of RA 9136; 4.3. Competitive Selection Process for Microgrid System Provider (CSP) refers to the procedure wherein an entity is awarded the contract to provide integrated power generation and distribution services to an unserved or underserved area through a transparent and competitive procedure, such as but not limited to, an auction, unsolicited proposal, or Swiss challenge, taking into consideration the requirements of the Act and other applicable laws; 4.4. Decentralized Power Generation (DPG) refers to small-scale power generation facilities which operate locally and are connected to the distribution system of the microgrid or end-user that could be aggregated to provide electric power necessary to meet demand, including, but not limited to, mini-wind turbines connected to a microgrid, energy storage, and solar photovoltaic rooftop of an end-user; 4.5. Distribution System refers to the system of wires and associated facilities extending between the delivery points on the transmission, sub transmission system, or power generation facility connection and the point of connection to the premises of the end-user, whichever is applicable; 4.6. Distribution Utility (DU) refers to any electric cooperative, private corporation, government-owned utility, or existing local government unit which has a franchise to operate a distribution system including those whose franchise covers economic zones; 4.7. DU Operated Microgrid System refers to a microgrid system owned and operated by a DU in a DU identified unserved area in its local total electrification roadmap; 4.8. Electric Cooperative (EC) refers to a DU organized pursuant to Presidential Decree No. 269, as amended, or as otherwise provided in the Act; 4.9. End-user refers to any natural or juridical person requiring the supply and delivery of electricity for its own use; 4.10. Grid refers to the high voltage backbone system of interconnected transmission lines, substations, and related facilities, located in each of Luzon, Visayas, and Mindanao; 4.11. Grid-tied Microgrid System refers to a microgrid system that is electrically connected to the distribution system of a DU and can operate in synchronized mode or in island mode; 4.12. Island Mode refers to a grid-tied microgrid system operating as a stand-alone system in supplying and delivering electric power to connected end-users; === dc2022-05-0017-pages-04.ppm === 4.13. Isolated Microgrid System refers to a microgrid system that is not electrically connected to a distribution system of a DU and is operating as a stand-alone system in supplying and delivering electric power to connected end-users; 4.14. Local Total Electrification Roadmap (LTER) refers to a DU's comprehensive 10- year strategic plan with an annual work plan to accelerate total electrification in its franchise area, to be updated annually; 4.15. Microgrid System refers to a group of interconnected loads and a generation facility or DPG with clearly defined electrical boundaries that acts as an integrated power generation and distribution system, whether or not connected to a distribution or transmission system; 4.16. Microgrid System Provider Service Contract (MSC) refers to the contract between the microgrid system provider and the National Power Corporation (NPC) whereby the microgrid system provider performs the missionary electrification function on behalf of the NPC and provides integrated power generation and distribution services in an unserved or underserved area, and to receive subsidy whenever applicable; 4.17. Microgrid System Provider (MGSP) refers to a natural or juridical person whose business includes the installation, operation, and maintenance of microgrid systems in unserved or underserved areas nationwide; 4.18. MGSP Proponent refers to any entity that is eligible to provide integrated power generation and distribution services in unserved and underserved areas; 4.19. National Total Electrification Roadmap (NTER) refers to a comprehensive national strategic plan including a work plan to accelerate total electrification in the country taking into account the various LTERs and the Distribution Development Plans (DDPs). It shall be incorporated in the Philippine Energy Plan; 4.20. NPC Graduation Plan refers to a comprehensive and detailed strategy of the NPC to attract private sector participation in areas purely served by the NPC; 4.21. Philippine Distribution Code (PDC) refers to the set of rules, requirements, procedures, and standards governing Distribution Utilities and Users of Distribution System in the operation, maintenance, and development of the Distribution System. It aiso defines and establishes the relationship of the Distribution System with the facilities or installations of the parties connected thereto; 4.22. Philippine Small Grid Guidelines refer to the rules, procedures, and requirements for the generation scheduling, dispatch, and control of active power, including provisions of ancillary service, if any, which are required to ensure power quality, reliability, and security of the Small Grid; 4.23. Private Investor-Owned Utility (PIOU) refers to private business organization which has an exclusive franchise to operate a distribution system; === dc2022-05-0017-pages-05.ppm === 4.24. Qualified Third Party (QTP) refers to the alternative electric service provider duly qualified and authorized by the ERC to serve Unviable Areas pursuant to Section 59 of the EPIRA and Rule 14 of the EPIRA-IRR; 4.25. Swiss Challenge refers to a competitive procurement system to be followed when projects are procured through unsolicited proposals from the MGSP Proponent; 4.26. Synchronized Mode refers to the operation of grid-tied microgrid systems whose generation facility or DPG is able to operate in the same frequency at its connection point to the distribution system of a DU, and allows the grid-tied microgrid system to supply to or draw power from the grid; 4.27. Underserved Area refers to a currently served area whose supply of electricity is less than twenty-four (24) hours daily because of the non-implementation of the approved capital expenditure projects, noncompliance with the service parameters of the PDC, or any other reason resulting to an overail failing mark based on ERC’s latest annual technical evaluation of the performance of distribution systems; 4.28. Universal Charge for Missionary Electrification (UC-ME) refers to the portion of the non-bypassable charge passed on and collected from all end-users on a monthly basis by the DUs pursuant to RA 9136, a portion of which is allocated for the provision of integrated power generation and distribution services in unserved and underserved areas not connected to the grid or within a franchise area where the distribution system is not connected to the grid; 4.29. Unserved Area refers to an area, upon the effectivity of the Act, with no electricity access, no distribution system lines, no home power systems, no connection to any microgrid system, or for which no distribution grid extension has been developed or implemented by the DU; and 4.30 Unsolicited Proposal (USP) refers to the proposal for the provision of electricity service in the unserved and underserved areas, submitted by an MGSP Proponent to the NPC, which is not in response to a solicitation or request issued by the latter. PART Il - Identification and Declaration of Unserved and Underserved Areas SECTION 5. Identification of Unserved Areas and Underserved Areas 5.1. Consistent with Section 15 of the Act, the DUs shalt submit to the DOE and integrate into its annual DDP, the LTER, which shall include a detailed inventory of all unserved and underserved areas within its franchise. 5.2. The NPC and NEA, in consultation with the DUs, shall recommend to the DOE the template of the LTER within thirty (30) calendar days from the effectivity of IRR, thereafter, the DOE shall issue the final template within fifteen (15) calendar days upon receipt of the recommended template. The LTER shall contain the following, among others: === dc2022-05-0017-pages-06.ppm === 5.3. 5.4. 5.5. 5.6. 5.7. 5.2.1. A validated detailed inventory of all Areas within a DU’s franchise that it plans to electrify including a specific time frame for electrification, including DU Identified Unserved Areas for electrification through DU operated microgrid systems; 5.2.2. A validated annual work plan for electrification; and 5.2.3. A validated detailed inventory of all Unserved and Underserved areas within its franchise. All projects in each annual work plan shall be completed not later than eighteen (18) months from submission to the DOE or, in the case of DU Identified Unserved Areas, from the lapse of the thirty (30) calendar day period for MGSPs to tender an all-in price offer pursuant to Section 14 of this IRR. For the DU Identified Underserved Areas included in the work plan, the submission shall include, but is not limited to, the following: 5.3.1. Technical and Financial Proposal; §.3.2. Load profile (projected total energy sales, peak demand, growth rate, etc); 5.3.3. Proposed Rate; 5.3.4. Demographic profile; and 5.3.5. Existing electricity provider. All LTERs shall be submitted by the DUs to the DOE or by the NEA, in the case of ECs, not later than the 15th of March every year. In the case of ECs, the NEA shall include its recommendations in the submission of the LTER. The DOE shall receive and validate any petitions from End-users pursuant to Section 6 of this IRR, and nominations from MGSP Proponents pursuant to Section 15 of this IRR, in consultation with NEA and NPC prior to the DOE’s declaration of Unserved and Underserved areas. The DOE shall prepare the NTER and publish it on the DOE website, no later than 30 September of every year. Unserved and Underserved Areas that already have an appropriation for electrification in the General Appropriations Act (GAA) at the time of the effectivity of the Act shall not be included in the list of DOE Declared Unserved and Underserved areas and DU Identified Unserved areas. SECTION 6. End-User Petition of Unserved and Underserved Areas 6.1. Any End-user residing in unserved or underserved areas not identified or included by the DU in its LTER or not declared by the DOE may file a petition to the DOE for possible declaration as unserved or underserved areas. The said petition shall include the following: Full name; Complete address; Contact details; Government-issued ID or other competent identifications; and Electricity service situation of the areas where the petitioner is residing. DAHA earner Geen Ger Ger ohwh — === dc2022-05-0017-pages-07.ppm === 6.2. 6.3. The DOE, in coordination with NPC, NEA, franchised DU, and other agencies shall verify the subject area/s qualification for possible inclusion in the list of DOE declared unserved and underserved areas. The verification shall not be longer than thirty (30) calendar days from the receipt of the petition. The NEA/NPC shall submit to the DOE its verification report including its proposed action to address the end-users petition. SECTION 7. Declaration of Unserved and Underserved Areas 7.1, 7.2. 7.3. DOE shall declare Unserved and Underserved areas indicated/identified in the following: 7.1.1. Atl Unserved and Underserved areas in the DU’s LTER not identified for DU Operated Microgrid System; 7.1.2 NPC-SPUG areas identified in their Graduation Plan pursuant to Section 16.3 of this IRR; 7.1.3 Verified petitioned areas pursuant to Section 6 of this IRR; and 7.14 Nominated areas pursuant to Section 15 of this IRR. The said declaration shall be published on the DOE website no later than the 30th of September every year. Unserved areas identified for electrification by DU Operated Microgrid Systems in their LTER shall be published by the DOE as DU Identified Unserved areas and shall undergo CSP pursuant to Section 14 of this IRR. The DOE Declared Unserved and Underserved areas or DU Identified Unserved areas which are awarded to MGSPs pursuant to Sections 13 and 14 of this IRR shall be deemed waived by the DU insofar as its obligation to provide distribution services and connections to end-users and supply electricity to the area concerned. The waiver shall not transfer, abandon, or modify the DU’s franchise but bestows upon the awarded and compliant MGSP the exclusive right and obligation during the existence of the MSC, on behalf of the NPC, to provide integrated power generation and distribution services to the unserved and underserved area during the period of the MSC, consistent with the NPC's missionary electrification function. The DU and the MGSP shall come to an agreement on the use of existing facilities and distribution system in the area awarded to the MGSP, either by way of sale, lease or usufruct or any other manner, during the term of the MGSP without jeopardizing the affordability of electricity rates in the said area. PART Ill. Qualification of MGSP SECTION 8. Eligibility Requirements 8.1. The participation as an MGSP shall be open to any party including private corporations, local government units, cooperatives, non-government organizations, === dc2022-05-0017-pages-08.ppm === generation companies, and their subsidiaries, and DU’s and their subsidiaries who have demonstrated the capability and willingness to comply with the relevant technical, financial, and other requirements as prescribed under the competitive selection process for MGSP; and 8.2. The ownership and operation of a microgrid system in Unserved and Underserved areas shall not be a public utility operation. The MGSP shall not be required to secure a franchise from Congress but shal! secure an ATO and COC from the ERC prior to its operation. Section 8. Guidelines for DU’s Joint Venture 9.1. A DU may enter into a joint venture for the installation and operation of microgrid systems. The DU shal! maintain a separate account for such business undertaking pursuant to the ERC’s applicable rules and guidelines on business separation and unbundling. Only a joint venture for the installation and operation of a microgrid system where the DU with a franchise in the area of operations owns at least fifty- one (51%) of capital shall be considered as a DU-operated microgrid system or a DU’s MGSP. 9.2. The NEA shall issue guidelines for the ECs entering into a joint venture within sixty (60) calendar days from the effectivity of this IRR. 9.3. A DU’s MGSP may participate in a CSP in a DOE Declared Unserved and Underserved area. It shal! have the right to tender a lower offer within the DU’s franchise area, except where the CSP is conducted in view of an expiring MSC under Section 21 of this IRR, in which case the MGSP with the expiring MSC over the area shall have the exclusive right to tender a lower offer. PART IV. Procedure for Electrification of Unserved and Underserved Areas through Microgrid System SECTION 10. Authorized Entity for the Conduct of CSP The DOE shall conduct the CSP, unless it has authorized the NPC or NEA to conduct the CSP, for the DOE Declared Unserved and Underserved Areas and the DU Identified Unserved Areas in the DU franchise area, pursuant to this IRR and subject to the delegated authority given by the DOE. SECTION 11. Bids and Awards Committee for MGSP 11.1. MGSP Bids and Awards Committee (MGSP BAC) A MGSP BAC shail be established and composed of members with verified proof of expertise or knowledge on procurement, finance or economics, law, and the Philippine electrical system. === dc2022-05-0017-pages-09.ppm === 11.1.1. 11.1.2. 11.1.3. 11.1.4, An independent MGSP BAC shall be established to spearhead and manage the CSP for MGSP. The MGSP BAC shall comply with the policy and procedures in the conduct of CSP for MGSP, as provided for in this IRR. The MGSP BAC shall be composed of five (5) members. The Chair and Vice-Chair shall be selected by the members of the MGSP BAC. The Chairman shall only vote in case of a tie. A quorum of the MGSP BAC shall be composed of a simple majority of all voting members of the MGSP BAC. 11.1.5. The MGSP BAC shall be posted on the DOE, NEA and NPC websites. 11.2. MGSP BAC Technical Working Group (TWG) and Secretariat The MGSP BAC TWG and MGSP BAC Secretariat shall be composed and headed by a regular or permanent employee, preferably an officer, to assist the MGSP BAC in the performance of its functions. 11.2.1. 11.2.2. 11.2.3. 11.2.4. The MGSP BAC TWG shail be composed of technical, legal, and financial personnel. The MGSP BAC TWG shall assist the MGSP BAC in the technical components of the CSP for MGSP, such as the development of the MSC, TOR, eligibility screening, evaluation of bids, and post-qualification. The MGSP BAC Secretariat shall provide administrative support to the MGSP BAC for this purpose and serve as the keeper of all records and documents relating to all CSP for MGSP conducted. The MGSP BAC Secretariat shall fully document each step of the CSP for MGSP and prepare and keep written minutes and unedited video recordings of ali the MGSP BAC meetings and proceedings. 11.3. Observers in the CSP for MGSP To assure all parties to the selection of MGSP that the process employed is conducted in an open, transparent, effective, efficient, and equitable manner, Observers will be invited in accordance with this IRR. 11.3.1. 11.3.2. 11.3.3. In any conduct of a CSP, the ERC, NPC or NEA shall serve as Observers. Observers shall not participate in the proceedings and shall have no right to vote; Observers shall be given invitations in writing and transmitted formally through any available modes at least seven (7) calendar days before the date of the procurement stages; === dc2022-05-0017-pages-10.ppm === 11.3.4. The invitations to the Observers shall be extended in all of the following stages of the CSP for MGSP: Pre-bid Conferences, Submission and Opening of Bids, Bid Evaluation, Post-qualification, Awarding, and Contract Signing; 11.3.5. Observers shall be allowed unrestricted access to the following documents upon their request: (a) minutes of CSP meetings; (b) Abstract of Bids; (c) post-qualification summary report; (d) video recording of CSP for MGSP proceedings; (e) opened proposals; (f) draft MSC template; (g) Bid Documents and other related documents; 11.3.6. Observers may submit their written comments and recommendations within seven (7) calendar days from the end of the CSP for MGSP activity or from the receipt of the documentation of the proceedings; 11.3.7. The absence of Observers will not nullify the CSP for MGSP proceedings; and 11.3.8. Observers may request the result of the bidding and other pertinent documents related to the conduct of the CSP for MGSP proceedings. Such a request shall be made before the approval of the ERC of the MSC. SECTION 12. Preparation of Bid Documents for the CSP for MGSP. 12.1. The Bidding Documents to be prepared shall include at the minimum the following: 12.1.1. Invitation to Bid; 12.1.2. Bidding Schedule; 12.1.3. Terms of Reference include, but are not limited to: 12.1.3.1. Load Profile (projected total energy sales, peak demand, growth rate, etc.); 12.1.3.2. Proposed Rate; 12.1.3.3. Demographic profile of the subject Area including the existing electricity provider; 12.1.3.4. Potential renewable energy resources; 12.1.3.5. Target date of project commissioning; 12.1.3.6. Plan for compliance with the Philippine Small Grid Guidelines; and 12.1.3.7. Plan for compliance with the Renewable Portfolio Standard Guidelines of Off-grid Areas. 12.1.4. Draft MSC. 12.2 The Bid Documents and TOR shall be prepared within forty-five (45) calendar days after the date of publication of the DOE Declared Unserved and Underserved Areas and the DU Identified Unserved Areas. If the NPC and/or NEA is authorized for the conduct of the CSP, the said Bid Documents and TOR shall be submitted to the DOE for review and evaluation. The DOE shall recommend changes to the Bid Documents and the TOR when necessary, within thirty (30) calendar days upon receipt from the NPC/NEA. 10 === dc2022-05-0017-pages-11.ppm === SECTION 13. CSP for MGSP in DOE Declared Unserved and Underserved Areas 13.1. Publication and Posting. The Invitation to Bid shall be: 13.1.1. 13.1.2. 13.1.3. 13.1.4. Issued within twenty (20) calendar days from the finalization of the bidding documents; Published in a newspaper of general circulation once weekly for two (2) consecutive weeks, and in addition, be published at least once in a newspaper of local circulation in the province where the unserved and underserved areas are located; Posted continuously in the websites of the DOE, NPC, and NEA in case of ECs, for fifteen (15) consecutive calendar days upon publication; and Posted at any conspicuous places within the concerned DU’s main office premises for fifteen (15) consecutive calendar days upon publication. 13.2. Pre-bid Conference 13.2.1. 13.2.2. 13.2.3. 13.2.4. 13.2.5. The MGSP BAC shall conduct a pre-bid conference to address the queries from the prospective bidders. The pre-bid conference shail discuss, among other things, the eligibility requirements, the TOR, and the technical, legal, and financial components of the MSC to be bid out. The MGSP BAC shall reply to the written queries or clarifications of the MGSP Proponents in the form of Supplemental/Bid Bulletins. Decisions of the MGSP BAC amending any provision of the Bidding Documents shall be issued in writing through a Supplemental/Bid Bulletin at least seven (7) calendar days before the deadline for the submission and receipt of bids. Supplemental/Bid Bulletins may be issued in the following circumstances: 13.2.5.1. A request of the MGSP Proponents for clarification(s) on or for an interpretation of any part of the Bid Documents; and 13.2.5.2. Upon the initiative of the MGSP BAC for purposes of clarifying or modifying any provision of the Bidding Documents. Any modification to the Bid Documents shall be identified as an amendment. 13.3. Receipt and Opening of Bids 13.3.1. An MGSP proponent shall submit its sealed bid proposal on or before the date and time indicated in the Invitation to Bid, which must be within forty- 11 === dc2022-05-0017-pages-12.ppm === 13.3.2. 13.3.3. five (45) calendar days to sixty (60) calendar days from its publication and posting. The opening of bids shall take place in the presence of qualified bidders and the MGSP BAC. The MGSP BAC shall open the bids after the deadline for the submission and receipt of bids. The time, date, and place of the opening of bids shall be specified in the Bidding Documents. The MGSP Proponents or their duly authorized representatives may attend the opening of bids. The MGSP BAC shall ensure the integrity, security, and confidentiality of all submitted proposals. In case the proposals cannot be opened as scheduled due to justifiable reasons, the MGSP BAC shall take custody of the bids submitted and reschedule the opening of bids on the next working day or at the soonest possible time through the issuance of a Notice of Postponement to be posted in the DOE or NPC’s website if any, and the NEA’s website for ECs. 13.4. Bid Evaluation Criteria and Process 13.4.1. 13.4.2. 13.4.3. The MGSP BAC shall proceed with the determination of the winning MGSP using the evaluation criteria prescribed in the Bid Documents. A bid that fails to meet all requirements in the Invitation to Bid shall not be considered. The first part of the bid shall undergo a pass/fail criteria based on financial, technical, and legal qualifications, while the second part shall consider the lowest price. The lowest calculated bid shall be subjected to a post-qualification process to determine whether the concerned bidder complies with and is responsive to all the requirements and conditions as specified in the TOR and other pertinent bidding documents. The following shall be the minimum criteria in the evaluation of the Technical and Financial Proposals: 13.4.3.1. Qualification of the Proponent — to include among others, the technical capacities and experiences of the key personnel/staff to execute the design & engineering, construction works and set up appropriate operations and management system, as well as the financial position of the proponent to undertake the project; 13.4.3.2. Proposed Technology — compliance with applicable rules and policies contained in the Philippine Small Grid Guidelines issued by the ERC and the Renewable Energy Portfolio Standards in Off-Grid Areas. The technology should be the least-cost option in providing 24/7 electricity service and will result in 100% household electrification in the area over the project term. 13.4.3.3. Institutional Arrangements — refer to the operation and maintenance arrangements, including billing and colfection, and disconnection, among others. 12 === dc2022-05-0017-pages-13.ppm === 13.4.3.4. Financial Proposal to include assumptions used in the project costing, adequate financing, life-cycle cost estimate, and formulation of its proposed full cost. 13.4.4. Upon MGSP BAC’s determination of the winning MGSP, the DU’s MGSP shall have the right to tender a lower all-in price offer within seven (7) calendar days after the MGSP BAC publishes all price offers it has received on its website. Such tender shall be submitted to the DOE or its authorized entity, whichever is applicable, and the winning bidder; or, Should the DU’s MGSP tender a lower offer, the MGSP BAC shall recommend the award for electrification of the unserved or underserved area using the Microgrid System to the DU’s MGSP. Otherwise, the MGSP BAC shall recommend the award to the winning MGSP. 13.4.5. The NPC and the winning MGSP shall execute the MSC within fifteen (15) calendar days after the conduct of a successful CSP, in accordance with the minimum terms and conditions as provided in the template. 13.4.6. The entire procedure from pre-qualification of MGSPs until the submission to the ERC of the awarded contract shall be no longer than ninety (90) calendar days after all the published requirements are completely submitted. 13.4.7. The award by the DOE or its authorized entity to the MGSP/DU, the execution of the MSC, and the filing of a complete application with the ERC shall be the basis of the issuance of a Notice/Acknowledgement or similar document and shall constitute the provisional authority of the MGSP/DU to start a collection of the rate specified in the award, the MSC, and the application upon the start of the MGSP’s operation. Accordingly, the ERC shall schedule and conduct a hearing thereon within thirty (30) calendar days from receipt of the complete application, upon publication and notice to all affected parties; and the ERC shail issue the final decision within one hundred thirty-five (135) calendar days from receipt of the complete application. 13.4.8. The Competitive Bidding for MGSP is deemed successful when it receives at least one (1) qualified bid. However, in the event that there are no participants or there is no awarded MGSP in the CSP for a particular DOE declared unserved or underserved area, the NPC shall perform its missionary electrification mandate in the said area until an MGSP takes part or is awarded in the next CSP. SECTION 14. CSP for MGSP in DU identified Unserved Areas 14.1. Publication and Posting. The Invitation to Bid shall be: 14.1.1 Issued within twenty (20) calendar days from the finalization of the bidding documents; 13 === dc2022-05-0017-pages-14.ppm === 14.1.2 14.1.3 14.1.4 Published in a newspaper of general circulation once weekly for two (2) consecutive weeks, and in addition, be published at least once in a newspaper of Socal circulation in the province where the unserved and underserved areas are located; Posted continuously on the websites of the DOE, NPC, and NEA in the case of the ECs, for fifteen (15) consecutive calendar days upon publication; and, Posted at any conspicuous piaces within the concerned DU’s main office premises for fifteen (15) consecutive calendar days upon publication. 14.2. Pre-bid Conference 14.2.1. The MGSP BAC shall conduct a pre-bid conference to address the queries from the prospective bidders. 14.2.2. The pre-bid conference shall discuss, among other things, the eligibility requirements, the TOR, and the technical, legal, and financial components of the MSC to be bid out. 14.2.3. The MGSP BAC shall reply to the written queries or clarifications of the MGSP Proponents in the form of Bid/Supp!emental Bulletins. 14.2.4. Decisions of the MGSP BAC amending any provision of the Bidding Documents shall be issued in writing through a Supplemental/Bid Bulletin at least seven (7) calendar days before the deadline for the submission and receipt of bids. 14.2.5. Supplemental/Bid Bulletins may be issued in the following circumstances: 14.2.5.1. A request of the MGSP Proponents for clarification(s) on or for an interpretation of any part of the Bid Documents; and, 14.2.5.2. Upon the initiative of the MGSP BAC for purposes of clarifying or modifying any provision of the Bidding Documents. Any modification to the Bid Documents shall be identified as an amendment. 14.3. Receipt and Opening of Bids 14.3.1. 14.3.2. 14.3.3. A MGSP proponent shall submit its sealed bid proposal on or before the date and time indicated in the Invitation to Bid, which must be within forty- five (45) to sixty (60) calendar days from its publication and posting. The opening of bids shall take place in the presence of qualified bidders and the MGSP BAC. The MGSP BAC shall open the bids after the deadline for the submission and receipt of bids. The time, date, and place of the opening of bids shall be specified in the Bidding Documents. The MGSP Proponents or their duly authorized representatives may attend the opening of bids. The 14 === dc2022-05-0017-pages-15.ppm === MGSP BAC shall ensure the integrity, security, and confidentiality of all submitted proposals. In case the proposals cannot be opened as scheduled due to justifiable reasons, the MGSP BAC shall take custody of the bids submitted and reschedule the opening of bids on the next working day or at the soonest possible time through the issuance of a Notice of Postponement to be posted in the DOE or NPC's website if any, and the NEA’s website for ECs. 14.4. Bid Evaluation Criteria and Process 14.4.1. 14.4.2, 14.4.3. 14.4.4, The MGSP BAC shall publish all price offers from the MGSP Proponent it has received on its website. A bid that fails to meet all requirements in the Invitation to Bid shall not be considered. The first part of the bid shall undergo a pass/fail criteria based on financial, technical, and lega! qualifications, while the second part shall consider the lowest price. The DU shall have the right to tender a lower all-in price offer within seven (7) calendar days after the MGSP BAC publishes all price offers. Should DU tender a fower offer, the MGSP BAC shall recommend the award for electrification of the unserved area using the Microgrid System to the DU. Otherwise, the MGSP BAC shail recommend the MGSP proponent with the lowest all-in price offer as the winning MGSP. The winning MGSP shail be subjected to a post-qualification process to determine whether the concerned bidder complies with and is responsive to all the requirements and conditions as specified in the TOR and other pertinent bidding documents. The following shal! be the minimum criteria in the evaluation of the Technical and Financial Proposals: 14.4.4.1. Qualification of the Proponent — to include among others, the technical capacities and experiences of the key personnel/staff to execute the design & engineering, construction works, and set up an appropriate operations and management system, as well as the financial position of the proponent to undertake the project; 14.4.4.2. Proposed Technology — compliance with applicable rules and policies contained in the Philippine Small Grid Guidelines issued by the ERC and the Renewable Energy Portfolio Standards in Off-Grid Areas. The technology should be the feast-cost option in providing 24/7 electricity service and will result in 100% household electrification in the area over the project term; 14.4.4.3. Institutional Arrangements — refer to the operation and maintenance arrangements, including billing and collection, and disconnection, among others.; and, 14.4.4.4. Financial Proposal to include assumptions used in the project costing, adequate financing, life-cycle cost estimate, and formulation of its proposed Full Cost Recovery Rate (FCRR). 15 === dc2022-05-0017-pages-16.ppm === 14.4.5. 14.4.6. 14.4.7. 14.4.8. The NPC and the winning MGSP/DU shall execute the MSC within fifteen (15) calendar days after the conduct of a successful CSP, in accordance with the minimum terms and conditions as provided in the template. The entire procedure from pre-qualification of MGSPs until the submission to the ERC of the awarded contract shall be no longer than ninety (90) calendar days after the publication by the DOE of the list of DU identified unserved areas. The award by the DOE or its authorized entity to the MGSP/DU, the execution of the MSC, and the filing of a complete application with the ERC shall be the basis of the issuance of a Notice/Acknowledgement or similar document and shall constitute the provisional! authority of the MGSP/DU to start a collection of the rate specified in the award, the MSC, and the application upon the start of the MGSP’s operation. Accordingly, the ERC shall schedule and conduct a hearing thereon within thirty (30) calendar days from receipt of the complete application, upon publication and notice to all affected parties; and the ERC shall issue the final decision within one hundred thirty-five (135) calendar days from receipt of the complete application. The Competitive Bidding for MGSP is deemed successful when it receives at least one (1) qualified bid. In the event there are no offers from any MGSP for a particular DU identified unserved area, the DU shail electrify the area through a DU operated microgrid system within eighteen (18) months from the lapse of the thirty (30) calendar day period for MGSPs to tender an all-in price offer. SECTION 15. Nomination of Areas by MGSP Proponents The Swiss Challenge for Unsolicited Proposal (USP) may be adopted as an alternative mode in selecting the MGSP in accordance with the guidelines prescribed under this IRR. 15.1. Requisites for Unsolicited Proposal The USP shall be considered when the target area is currently assigned to or served by the NPC or all of the following conditions exist: 15.1.1. 15.1.2. The target area is an unserved or underserved area; and The target area is not yet published as DOE declared unserved or underserved area or DU identified unserved area in the DOE’s NTER. 15.2. Submission of a Complete USP The MGSP proponent shail submit the following USP documents to the DOE or its authorized entity, whichever is applicable: 15.2.1. Cover letter expressing its interest; 16 === dc2022-05-0017-pages-17.ppm === 15.2.2. 15.2.3. Proof of Eligibility, as provided in Annex “A” “Checklist of Requirements for MGSP; and, Project Proposal which shall contain the following, at the minimum: 15.2.3.1. Proposed electrification solution or technology to be applied for the target area including the system design for the generation and distribution lines and proposed plans for dealing with major operating contingencies such as failure of its generating pfant or a major fault on its distribution system; 15.2.3.2. Number of potential and target household connections; 15.2.3.3. Proposed institutional and commercial arrangements ({i.e., meter reading, billing and collection, disconnection policies, etc.) 15.2.3.4. Expected date of commissioning/commercial operation of the project; 15.2.3.5. Work Plan with target dates, detailing the schedule of the significant activities to be taken towards project completion including the target date of application with the ERC for the issuance of the Authority to Operate (ATO); and 15.2.3.6. Proposed FCRR and other charges to end-users. 15.3. Receipt and Acceptance of the USP 15.3.1. 15.3.2. 15.3.3. Upon receipt of the USP, the MGSP BAC shall check the presence or absence of the required documents as provided under Section 15.2. of this IRR. The MGSP BAC shall only accept the USP with complete documents. The MGSP BAC shall inform the Proponent of the completeness of the submitted documents within five (5) calendar days from receipt. For incomplete submissions, ali documents shall be returned to the Proponent. In case the first USP is not accepted, the MGSP BAC shall proceed to check the completeness of the submitted documents under Section 15.2 of this IRR of the other MGSP Proponents, if any, using the First-In-Time Approach pursuant to Section 15.4.3. 15.4. Evaluation of the USP 15.4.1. The following shalt be the minimum criteria in the evaluation of the Technical and Financial Proposals: 15.4.1.1. Qualification of the Proponent — to include among others, the technical capacities and experiences of the key personnel/staff to execute the design & engineering, construction works.and set up appropriate operations and management system, as well as the financial position of the proponent to undertake the project; 15.4.1.2. Proposed Technology — compliance with applicable rules and policies contained in the Philippine Smail Grid Guidelines issued by the ERC and the Renewable Energy Portfolio 17 === dc2022-05-0017-pages-18.ppm === 15.4.2. 15.4.3. 15.4.4. Standards in Off-Grid Areas. The technology should be the least-cost option in providing 24/7 electricity service and will result in 100% household electrification in the area over the project term; 15.4.1.3. Institutional Arrangements — refer to the operation and maintenance arrangements, including billing and collection, and disconnection, among others; and 15.4.1.4. Financial Proposal to include assumptions used in the project costing, adequate financing and life-cycle cost estimate, and formulation of its proposed FCRR. The MGSP BAC shall evatuate and inform the Proponent whether the USP is qualified or not within thirty (30) calendar days from receipt of USP pursuant to Section 15.3.1. For unqualified USP, all documents shall be returned to the MGSP Proponent. The MGSP BAC may proceed with the evaluation of another MGSP proponent. If none of the MGSP Proponents will qualify, a CSP shall be conducted pursuant to Section 13 of this IRR after the posting of the area as DOE declared an unserved or underserved area. In case the MGSP BAC receives more than one USP involving the same target area prior to the declaration of the first USP as the “Original Proposal’, the MGSP BAC shall evaluate the proposals using the First-In- Time approach. 15.4.3.1. Under the First-In-Time approach, the complete USP first received by the MGSP BAC shail primarily be evaluated and decided upon. Subsequent submitted USP will only be evaluated if the first one is not qualified, based on the order of their submission. 15.4.3.2. The MGSP BAC shall acknowledge the USP submissions of other MGSP Proponents for a similar target area and advise the said MGSP Proponents of the existence of similar proposal(s) and its rank/position based on the date of receipt. 15.4.3.3. If the USP has been declared as the “Original Proposal’, other Proposals shall be returned to the respective proponents unopened. The MGSP BAC shall subsequently declare the MGSP Proponent as the Original Proponent and its accepted USP as the “Original Proposal’, and shall prepare the TOR and the corresponding Bidding Documents. 15.5. Preparation and Review of Bid Documents 15.5.1. The MGSP BAC shall prepare the Bid Documents based on the Original Proposal of the Original Proponent which includes at the minimum the following: 15.5.1.1. Invitation to Bid; 15.5.1.2. Bidding Schedule; 18 === dc2022-05-0017-pages-19.ppm === 15.5.1.3. 15.5.1.4. Terms of Reference that include, but are not limited to, the following data from the USP: Projected load profile; Type of offered technology; Proposed energy generated for the term period; Target number of households; Demographic profile of the target area including the existing electricity provider; Full Cost Rate; and Target date of Commercial Operations. Draft MSC in accordance with the template provided by the DOE. 15.5.2. The Bid Documents and TOR shall be prepared within forty-five (45) calendar days after the date of publication of the Declared Unserved and Underserved Areas and the DU Identified Unserved Areas. If the NPC and/or NEA is authorized for the conduct of the CSP, the said Bid Documents and TOR shall be submitted to the DOE for review and evaluation. The DOE shall recommend changes to the Bid Documents and the TOR when necessary, within thirty (30) calendar days upon receipt from the NPC/NEA. 15.6. Swiss Challenge for Unsolicited Proposal The Original Proposal shall be subjected to a Swiss Challenge. 15.6.1. Publication and Posting The target area shall be published and posted on the DOE websites and be included in the list of DOE declared unserved or underserved areas. Such publication shall also serve as the Invitation to Bid. 15.6.2. Pre-bid Conference 15.6.2.1. 15.6.2.2. 15.6.2.3. The MGSP BAC shall conduct at least one (1) Pre-Bid Conference to address the queries of the prospective bidders within fourteen (14) calendar days after the publication of the Invitation for Comparative Proposal. The pre-bid conference shall discuss, among other things, the eligibility requirements, the TOR and technical, legal, and financial components of the MSC to be bid out. Requests for clarification to the MGSP BAC from the prospective MGSP Proponents shall be made in writing or through electronic mail before the conduct of the Pre-bid Conference, or after three (3) calendar days from the scheduled Pre-bid Conference, and through manifestation(s) during the Pre-bid Conference. 19 === dc2022-05-0017-pages-20.ppm === 15.6.2.4. 15.6.2.5. 15.6.2.6. 15.6.2.7. 15.6.2.8. The MGSP BAC shall reply to the written queries or clarifications of the MGSP Proponents in the form of Bid/Supplemental Bulletins. Decisions/clarifications of the MGSP BAC amending any provision of the Bidding Documents shall be issued in writing through a Supplemental/Bid Bulletin at least seven (7) calendar days before the deadline for the submission and receipt of bids. Supplementai/Bid Bulletins may be issued in the following circumstances: 15.6.2.6.1. Request of the MGSP Proponents _ for clarification(s) on or before an interpretation of any part of the Bid Documents; and, 15.6.2.6.2. Upon the initiative of the MGSP BAC for purposes of clarifying or modifying any provision of the Bidding Documents. Any modification to the Bid Documents shall be identified as an amendment. Pre-bid Conference shall be conducted within fourteen (14) calendar days upon the posting of the invitation for comparative proposal. The MGSP BAC shall ensure that all clarifications and queries must be clarified by the issuance of Supplemental/Bid Bulletins, and shall avoid any delay in the conduct of the Swiss Chailenge. 15.6.3. Receipt and Opening of Comparative Proposals 15.6.3.1. 15.6.3.2. 15.6.3.3. An MGSP Proponent shall submit its sealed comparative proposal on or before the date and time indicated in the Invitation to Bid, which must not be Jater than forty-two (42) calendar days from its publication and posting. Comparative proposals submitted after the deadline shall no longer be accepted. The MGSP Proponents shall submit their proposals through their duly authorized representative using the forms specified in the Bidding Documents in two (2) separate sealed bid envelopes which shall be submitted simultaneously. The first shall contain the technical component of the bid, including the eligibility requirements, and the second shall contain the financial component of the bid. The MGSP BAC shall open the bids after the deadline for the submission and receipt of bids. The time, date, and place of the opening of bids shall be specified in the Bidding Documents. The MGSP Proponents or their duly authorized representatives may attend the opening of bids. The MGSP BAC shall ensure the integrity, security, and confidentiality of all submitted proposals. In case the proposals cannot be opened as scheduled due to justifiable reasons, the MGSP BAC shall take custody of the 20 === dc2022-05-0017-pages-21.ppm === 15.6.4. 15.6.3.4. bids submitted and reschedule the opening of bids on the next working day or at the soonest possible time through the issuance of a Notice of Postponement to be posted in the DOE or NPC's website if any, and the NEA’s website for ECs. The opening of bids shall take place in the presence of qualified bidders, Observers, and the MGSP BAC. The absence of an MGSP Proponent shall not be a ground for the postponement of the opening of bids or disqualification of the MGSP Proponent. Bid Evaluation of the Comparative Proposals 15.6.4.1. 16.6.4.2. 15.6.4.3. 15.6.4.4. 15.6.4.5. 15.6.4.6. The MGSP BAC, after the submission of the comparative proposal, shall undergo a qualification and evaluation process of the legal, technical, and financial requirements submitted by proponents using the criteria indicated in the Bidding Documents. The MGSP BAC shall recommend, in fourteen (14) calendar days, the declaration of the lowest comparative proposal as the lowest calculated bid. Upon the declaration, the MGSP BAC shall immediately notify in writing the Original Proponent, if not present. The Original Proponent shall have the right to match such price proposal within fifteen (15) calendar days from receipt of the notification from the MGSP BAC of the result of the comparative bid. In case the Original Proponent fails to match the price proposal of the lowest calculated bid within the specified period, the comparative proponent/lowest calculated bidder shall be the winning bidder. On the other hand, if the Original Proponent matches the price proposal of the comparative proponent/lowest calculated bidder within the specified period, the Original Proponent shalt be the winning bidder. The Original Proponent shall be the winning bidder in case of the following conditions: 15.6.4.5.1. No comparative bid was received by the MGSP BAC; or, 15.6.4.5.2. Comparative bids failed to meet the requirements prescribed in the bid documents. The MGSP BAC shall conclude the selection of the winning MGSP within fifty (50) calendar days from the opening of the Comparative Bids and correspondingly recommend the issuance of the Notice of Award. 21 === dc2022-05-0017-pages-22.ppm === 15.6.4.7. The NPC and the winning MGSP shall execute the MSC within fifteen (15) calendar days after the conduct of the successful bidding, in accordance with the template provided by the DOE. SECTION 16. NPC Missionary Electrification 16.1. 16.2. 16.3. In the event that there are no participants or there is no awarded MGSP in the CSP pursuant to Section 13 of this IRR, and upon declaration of failed CSP, the NPC shall continue to perform its missionary electrification function by energizing the said area within eighteen (18) months from the availability of funding source, provided it shall be given priority by the NP Board. NPC shall continue to energize the area until an MGSP takes part or is awarded in the next CSP. The NPC shall source the funding for the energization from the National Government or other identified fund sources and grants. The NPC shall prepare and submit to the DOE a comprehensive and detailed Graduation Plan within one hundred eighty (180) calendar days upon effectivity of this IRR and shall be updated annually. The said plan shall include, but is not limited to, the following: 16.3.1. Areas to be included in the list of DOE declared Unserved and Underserved Areas; and, 16.3.2. Criteria for inclusion of areas in the DOE are declared Unserved and Underserved areas. PART V. Regulatory Framework SECTION 17. Permitting Process 17.1. 17.2. 17.3. 17.4, 17.5. A Notice or Acknowledgement or similar document shall constitute the provisional authority to be issued by the ERC within seventy-five (75) calendar days upon award by the DOE or its authorized entity to the MGSP/DU, the execution of the MSC, and the receipt of a complete application by the MGSP/DU with the ERC. A hearing shail be scheduled and conducted by the ERC within thirty (30) calendar days from receipt of the complete application, upon publication and notice to all affected parties. The final decision relative to the application for ATO shall be issued by the ERC within one hundred thirty-five (135) calendar days from receipt of the complete application. A COC shall be secured from the ERC prior to the commercial operation of the MGSP. Republic Act No. 11234, otherwise known as the “Energy Virtual One-Stop Shop Act”, shall apply to the permitting process of all MGSPs: Provided, That the applicable time frame shall be reduced to half of the time frame indicated in 22 === dc2022-05-0017-pages-23.ppm === Sections 13, 14,15, and 16 of Republic Act No. 11234 unless the specific time frame is provided in the Act or in this IRR. SECTION 18. Issuance of Rates 18.1. The ERC shall evaluate and determine an MGSP or DU-operated microgrid system’s full cost, approved subsidy if applicable, and retail rate imposed on end- users of unserved and underserved areas. 18.2. The ERC shall issue rules on the UC-ME availment in accordance with DOE's existing policy on subsidy rationalization within one hundred twenty (120) calendar days upon effectivity of this IRR. SECTION 19. Technical and Services Performance Standards The ERC shail develop, establish, and promulgate in consultation with the DOE, NPC, NEA and other relevant government agencies and private stakeholders in the electric power industry, the minimum technical and service performance standards for microgrid systems within one hundred twenty (120) calendar days from the effectivity of the Act: Provided, That these standards shall be compliant with the PDC, Philippine Small Grid Guidelines, Philippine Grid Code, and other relevant rules and regulations PART VI. Administration of UC-ME Subsidy SECTION 20. Collection and Disbursement Procedure 20.1. The ERC within ninety (90) calendar days upon effectivity of this IRR, shall issue a resolution on the recovery, collection, and availment of UC-ME by NPC for the microgrid. 20.2. The NPC shall submit to the ERC, within sixty (60) calendar days upon effectivity of this IRR, the guidelines for the disbursement of UC-ME to MGSPs. 20.3. The procedure for the release of the UC-ME subsidy shall not be more than forty- five (45) calendar days from submission to the NPC of the UC-ME subsidy claim with complete documentary requirements. PART Vil. Procedure for the Transition of Service SECTION 21. Expiration of MSC In the event of a distribution grid extension upon the expiration of an MSC, the DU shall have the option to acquire the microgrid system of the MGSP, and resume its obligation to provide distribution services and connection and supply electricity to the said area subject to the approval of the ERC and pursuant to Section 22 of this IRR. Should there be no distribution grid extension upon the expiration of an MSC, a CSP shall be conducted pursuant to Sections 13 or 14 of this IRR, whichever is applicable: Provided, That the MGSP with the expiring MSC over the area that participates in such CSP shall have the exclusive right to tender a lower offer within seven (7) calendar days from the announcement of the winning MGSP in the CSP. 23 === dc2022-05-0017-pages-24.ppm === SECTION 22. Detailed Transition of Service Procedure The DOE together with the NPC shall issue, within one hundred eighty (180) calendar days upon effectivity of this IRR, a detailed procedure for the transition of service from the NPC or a DU to an MGSP, or from an existing MGSP to a DU or another MGSP. Provided, that such transition shall not exceed ninety (90) calendar days from the completion of the CSP. PART Vill. Functions and Responsibilities SECTION 23. DOE The DOE shall: 23.1. 23.2. 23.3. 23.4. 23.5. 23.6. 23.7. 23.8. 23.9. Prepare and publish annually on its website the NTER, upon consultation with public and private stakeholders; Determine, in consultation with DUs, the time frame for compliance with their respective LTERs and DDPs: Provided, that all projects in each annual work plan shall be completed not later than eighteen (18) months from submission to the DOE or, in the case of DU identified unserved areas, from the lapse of the thirty (30) calendar day period for MGSPs to tender an all-in price offer pursuant to Section 14 of the IRR; Receive and verify petitions from end-users, who are currently residing in an unserved or underserved area not identified or included by the DU in its LTER or not declared by the DOE as such, to declare such area as an unserved or underserved area; Identify and declare regularly unserved and underserved areas; Conduct all CSPs for the DOE Declared Unserved and Underserved areas and the DU Identified Unserved areas with the assistance of the NPC and NEA in accordance with Section 10 of this IRR. Monitor the operations of all awarded MGSPs and their respective MSCs: Provided, That the DOE, motu proprio or upon complaint, may conduct a review of an MGSP’s operation and its corresponding MSC should it find reasonable grounds for noncompliance with the minimum technical and service performance standards and other provisions of the MSC; Determine a detailed procedure for the transition of service from the NPC or a DU to an MGSP, or from an MGSP to a DU or another MGSP, whichever is applicable; Provide support to the ERC in the development and promulgation of the minimum technical and service performance standards for microgrid systems consistent with Section 19 of this IRR; Modify the timelines regarding submissions of documents in consultation with the concerned stakeholders and in compliance with the provisions of the Act; and, 24 === dc2022-05-0017-pages-25.ppm === 23.10. Perform such other powers and functions as may be necessary to attain the objectives of the Act. SECTION 24. ERC The ERC shall: 24.1. 24.2. 24.3. 24.4. 24.5. 24.6. 24.7. 24.8. Provide for a simplified and streamlined permitting process for MGSPs and DU operated microgrid systems in accordance with the time frame specified in Section 17 of this IRR, and issue an ATO and COC to an MGSP pursuant to such process; Develop, establish, and promulgate in consultation with the DOE, the NPC, the NEA, and other relevant government agencies and private stakeholders in the electric power industry, the minimum technical and service performance standards for microgrid systems within one hundred twenty (120) calendar days from the effectivity of the Act: Provided, that these standards shall be compliant with the PDC, PSGG, Philippine Grid Code, and other relevant rules and regulations; Review and act on all MSCs entered into within the time frame consistent with Section 17 of this IRR; Exercise its rate-making power through the evaluation and determination of the following, within the applicable time frames provided under Section 17 of this IRR: 24.4.1. An MGSP or DU operated microgrid system's full cost, approved subsidy if applicable, and retail rate imposed on end-users of unserved and underserved areas; 24.4.2. An equitable recovery mechanism, if applicable, for an MGSP'’s assets to ensure just compensation at the expiration of the MSC pursuant to Section 17 of the Act; and, 24.4.3. In the event of a distribution grid extension, upon the expiration of the MSC, and upon the decision of the DU to acquire the microgrid system, review the application of the DU before the ERC to connect the microgrid system to the distribution grid pursuant to the equitable recovery mechanism provided in this section provided that any connection that results in an increase in rates shail have to be approved by the ERC. Monitor the compliance of all MGSPs with their obligations under their respective ATOs and COCs; Issue rules for the UC-ME availment of MGSPs in accordance with the DOE Rationalization Policy for UC-ME; Issue a resolution on the recovery, collection, and availment of UC-ME by the NPC for microgrid; Exercise original and exclusive jurisdiction over all cases involving the exercise of the abovementioned powers, functions, and responsibilities, and overall cases 25 === dc2022-05-0017-pages-26.ppm === 24.9. involving disputes arising from the Act, except in competition cases under Republic Act No. 10667, otherwise known as the “Philippine Competition Act”; and, Process any DU’s application for renewal of Certificate of Public Convenience and Necessity even with the presence of an MGSP in its franchise area pursuant to Section 18 of the Act. SECTION 25. NEA The NEA shall: 25.1. Assist ECs in the preparation of their respective LTERs; 25.2. Evaluate and verify the unserved and underserved areas submitted by ECs as part of its LTER and submit its recommendations to the DOE not later than the 15th of March of every year; 25.3. If authorized by the DOE to conduct CSPs pursuant to Section 10, strictly comply with the procedure, guidelines and timeframe for CSPs pursuant to Sections 11 to 15 of this IRR. 25.4. Provide support to the ERC in the development and promulgation of the minimum technical and service performance standards for microgrid systems consistent with Section 19 of this IRR; 25.5. Provide support in the DOE’s issuance of Guidelines of the Technical, Financial, and other requirements for an MGSP in coordination with the NPC and TRANSCO; and, 25.6. Issue guidelines for the Joint Venture engagement of ECs. SECTION 26. NPC The NPC shall: 26.1. 26.2. 26.3. 26.4. 26.5. Prepare and execute annually an NPC Graduation Plan pursuant to Section 16.2 of this IRR; Continue to perform its missionary electrification mandate, including areas with no participating or awarded MGSP during a CSP pursuant to Section 16.1 of this IRR; If authorized by the DOE to conduct CSPs pursuant to Section 10, strictly comply with the procedure, guidelines and timeframe for CSPs pursuant to Sections 11 to 15 of this IRR. Execute the MSC with the awarded MGSP/DU in accordance with the minimum terms and conditions as provided in the template; Exclusively collect from the DUs, administer, and apply the UC-ME; 26 === dc2022-05-0017-pages-27.ppm === 26.6. Provide simplified and streamlined procedures and requirements for the processing of UC-ME subsidy claims, upon consultation with public and private stakeholders; 26.7. Release the UC-ME subsidy within forty-five (45) calendar days from submission to the NPC of the UC-ME subsidy claim with complete documentary requirements; 26.8. Provide support in the DOE’s issuance of Guidelines of the Technical, Financial, and other requirements for an MGSP in coordination with the NEA, and TRANSCO; 26.9. Provide support to the ERC in the development and promulgation of the minimum technical and service performance standards for microgrid systems consistent with Section 19 of this IRR; and, 26.10. Provide support in the determination and establishment of a detailed procedure for the transition of service from the NPC or a DU to an MGSP, or from an MGSP to a DU or another MGSP, whichever is applicable. SECTION 27. DU The DU shall: 27.1. Develop the LTER to be submitted annually to DOE or through the NEA in the case of the ECs; 27.2. Integrate the LTER in its DDP; and 27.3. DU may enter into a joint venture for the installation and operation of microgrid systems consistent with the requirements of Section 15 of the Act. SECTION 28. MGSP Proponent The MGSP Proponent shall: 28.1. Secure the necessary permits and licenses from the relevant government agencies; and, 28.2. Comply with all provisions, including the financial, technical, environmental, and other performance standards for the MGSP including the provision of the MSC entered into with the NPC. SECTION 29. MGSP and DU’s MGSP The MGSP and DU's MGSP shall: 29.1. Build, operate, maintain, and control its microgrid system in accordance with its MSC, the Act, and other applicable laws, rules, regulations, and codes; 29.2. Supply the load requirements of its area of operation, faithfully implement its electrification work program, and comply with all its obligations under its MSC, if applicable; 27 === dc2022-05-0017-pages-28.ppm === 29.3. Prepare and submit any report required by the ERC and DOE pursuant to their powers under Sections 11 and 12 of the Act; 29.4. Ensure end-user safety and protection at all times; and, 29.5. In the case of MGSPs, be exempt from the following: 29.5.1. The public listing requirement under Section 28 of RA 9136, and, 29.5.2. The market share limitation requirement under Section 45(a) of RA 9136. 29.6. The end-users in unserved areas and underserved areas not connected to the grid or within a franchise area where the distribution system is not connected to the grid shall be exempt from the following: 29.6.1. The payment of feed-in-tariff (FIT) allowance under the FIT system in Section 7 of Republic Act No. 9513, otherwise known as the “Renewable Energy Act of 2008”, and, 29.6.2. The payment of universal charges under Section 34 of RA 9136. SECTION 30. Strengthening and Expansion of the Electric Power Industry Management Bureau in the Department of Energy Within one hundred eighty (180) calendar days from the effectivity of the IRR, the Secretary of the DOE shall submit the organizational structure and staffing complement, which shall be effective upon the approval of the Department of Budget and Management, consistent with existing civil service rules and regulations. Pending the approval of the organizational structure and staffing complement, the Secretary of the DOE may designate personnel from EPIMB and its support units to perform the duties, functions, and responsibilities under the Act and its IRR. SECTION 31. Creation of a Special Division in the Energy Regulatory Commission A special Division attached to the appropriate Service Department in the ERC is hereby created for the effective implementation of the Act. The new organizational structure and staffing complement shall be determined by the Commission and approved by the Office of the President in accordance with the existing laws, rules, and regulations. The budgetary requirements shall be taken from the current appropriations of the ERC. Thereafter, the funding for the dedicated division shail be included in the GAA. SECTION 32. NPC’s Authority to Secure Required Resources To effectively perform its mandate under this IRR, NPC is hereby authorized to secure resources, including but not limited to financial, human, and logistics, among others to fully comply with its duties and responsibilities. SECTION 33. Transition from Revised QTP Guidelines On-going selection of Qualified Third Party pursuant to Department Circular Nos. DC2004-06-006, DC2005-12-011 and DC2019-11-0015, shall only proceed when the 28 === dc2022-05-0017-pages-29.ppm === DOE or DU conducted its bid opening and a qualified QTP has been selected on or before the effectivity of this IRR. PART IX. Prohibited Acts and Criminal and Administrative Penalties SECTION 34. Prohibited Act Any person, natural or juridical, is prohibited from the following acts: 34.1. 34.2. 34.3. 34.4, 34.5. Refusal to allow the installation of any microgrid system by an MGSP: Provided, That the requirements under Sections 5, 6, 7, 8, and 9 of the Act are complied with; Refusal to turn over the provision of integrated power generation and distribution services to an MGSP, or distribution services and connection and supply of electricity to a DU, whichever is applicable; Refusai to allow a DU to acquire a microgrid system pursuant to Section 17 of the Act; Imposition of new contractual terms and charges on the end-user which are not part of the MSC or not approved by the ERC, whichever is applicable; and, Failure to comply with the functions, responsibilities, and time frames in Sections 5 to 19 of the Act. SECTION 35. Criminal and Administrative Penalties 35.1. The responsible officers and employees of any private corporation or government agency who commit the following prohibited acts shall, upon conviction, suffer the following penalties: 35.1.1. Violation of Section 23(a), (b), and (c) - Imprisonment of six (6) years to eight (8) years, or a fine ranging from a minimum of Seventy-five million pesos (P75,000,000.00) to One hundred million pesos (P100,000,000.00), upon the discretion of the court; 35.1.2. Violation of 23(d) - Imprisonment of four (4) years to six (6) years, ora fine ranging from a minimum of Fifty million pesos (P50,000,000.00) to Seventy-five million pesos (P75,000,000.00); and 35.1.3. Violation of Section 23(e) - Imprisonment of two (2) years to four (4) years, or a fine ranging from a minimum of Twenty-five million pesos (P25,000,000.00) to Fifty million pesos (P50,000,000.00), upon the discretion of the court. Any person who willfully aids or abets the commission of these prohibited acts or who causes the commission of any such act by another shall be liable in the same manner as the principai. In cases of an association, partnership, or corporation, the penalty shall be imposed on the member, partner, president, chief operating officer, chief executive officer, director, or officer responsible for the violation. 29 === dc2022-05-0017-pages-30.ppm === 35.2 Without prejudice to the aforementioned criminal liabilities, any government officer, or employee who violates Section23(e) of the Act shall be held administratively liable, as follows: 35.2.1. First offense - Thirty (30) calendar days suspension without pay and mandatory attendance in Values Orientation Program; 35.2.2. Second offense - Three (3) months suspension without pay; and, 35.2.3. Third offense - Dismissal and perpetual disqualification from public service, and forfeiture of retirement benefits. PART X. Final Provision SECTION 36. Amendatory Clause This IRR amends Section 16(c) of Commonwealth Act No. 146 otherwise known as the “Public Service Act”; Section 8 of Executive Order No. 172 Series of 1987, entitled “Creating the Energy Regulatory Board”; Sections 28, 43, 45(a), 51(I), 59, and 70 of Republic Act No. 9136; Sections 13, 14, 15, and 16 of Republic Act No. 11234; and any other law, presidential decree or issuance, executive order, letter of instruction, rules, and regulations inconsistent with the provisions of this Rule. SECTION 37. Separability Clause If any portion or provision of this IRR is declared unconstitutional, the same shall not affect the validity or the legality of the other provisions. SECTION 38. Repealing Clause Any law, presidential decree or issuance, executive order, letter of instruction, rules, and regulations, and legislative or administrative franchises inconsistent with the provisions of this Rule is hereby repealed or modified accordingly. SECTION 39. Effectivity These Rules shall take effect fifteen (15) calendar days following its complete publication in at least two (2) newspapers of general circulation. Copies thereof shall be filed with the University of the Philippines Law Center — Office of National Administrative Register (UPLC-ONAR). Issued on MAY 2 L 2022 at Energy Center, Bonifacio Global City, Taguig City. Ma, Secretary Repubiic of the Philippines OEPARTMENT OF ENERGY IN REPLYING PLS, CITE: DOE-AGC-22002880 EQUATION 30 === dc2022-05-0017-pages-31.ppm === Republic of the Philippines DEPARTMENT OF ENERGY Energy Center, Rizal Drive corner 34" Street Bonifacio Global City, Taguig City Metro Manilla Annex A CHECKLIST OF REQUIREMENTS FOR MICROGRID SYSTEM PROVIDERS A. Legal Requirements 1. Individual or Proprietorship oO a QO oOo Birth Certificate issued by the Philippine Statistics Authority Current Business Permit Department of Trade and industry (DTI) Registration (if applicable) Special Power of Attorney to Negotiate and Enter into MGSP Service Contract with EC 2. Corporation/ Joint Venture/ Consortium/ Cooperative a By-Laws (BL) and Articles of Incorporation (AOI), and BL and AOI! of its corporate stockholders Board Resolution authorizing its representative to negotiate and enter into QSC with the DU/NPC Latest General information Sheet (GIS) and latest GIS of its corporate stockhoiders Current Business Permit Organizational Chart of the Company 3. Passport ID or any valid government-issued !D of the authorized representatives, i.e., signatory and witness under the QSC B. Technical Requirements 1. Full details of the technical skills and experience of the key management team responsible for the operation of the system. These details should include relevant technical and business management qualifications as well as full descriptions of experience relevant to the technical and commercial operation of electric power generation and supply systems. 2. Details of the proposed arrangements for the acquisition, training and contracting of the necessary expertise that the applicant does not possess at the time of application. 3. A statement certifying that the applicant intends to design, construct, operate and maintain its generation and distribution systems in full compliance with the relevant requirements prescribed under the applicable laws including EPIRA and its attendant rules and regulations C. Financial Requirements o Latest Annual Report and/or Audited Financial Statements (FS) for the last two (2) years from the filing date and latest Unaudited FS duly signed by the Document Format Original or PSA Certified Copy Certified True Copy Certified True Copy Original Copy Original SEC-Certified or CDA- Certified or NEA-Certified Original Copy Certified True Copy of SEC- Received Certified True Copy Certified True Copy Certified True Copy Print Copy Print Copy Notarized Copy Original or Certified True Copy responsible official such as the President and/or Chief Finance Officer if the Audited FS is more than six (6) months old at the time of filing. === dc2022-05-0017-pages-32.ppm === co Bank certification to substantiate the cash balance in the Audited FS or unaudited FS O Projected Cash Flow Statement for next two (2} years, except for geothermal and large hydro resources which should be five (5) years, showing the fund sources and uses of funds for the particular offered area, other applied RE areas, existing service/operating contracts with DOE and other existing business, if applicable, with supports from either of the following: ca Sworn Letter of Commitment from stockholders for additional equity/cash infusion o Bank approved loan/credit jine earmarked for the proposed operation For applicants with insufficient funds to finance the propased operations: O Newly organized corporation (existing for two (2) years or less from date of registration with SEC) should be supported by parent company’s financial documents per items 1 and 2 above and Letter of Guaranty by the parent company to fund the work program. O Subsidiary corporation (existing for more than two (2) years from date of registration with SEC) should be supported by the following: QO Notarized Letter of Guaranty from the majority shareholder/s and Original Bank proof of capacity to satisfy the said Guaranty Certification; or Q Parent company’s financial documents per items 1 and 2 above and Letter of Guaranty by the parent company to fund the work program/pian Q_ Incase of domestic parent company, the Letter of Guaranty should be duly notarized. © In case of foreign parent company, the documents shail be duly authenticated by the Philippine Consulate Office that has jurisdiction over the said parent company. Original Copy Original Copy Original Copy Certified True Copy Original Copy Original Copy Original Copy Notarized Copy Consularized Copy