=== dc2013-12-0027-pages-1.ppm === Republic of the Philippines DEPARTMENT OF ENERGY DEPARTMENT CIRCULAR NO, DC 2013-12 - 0027 DECLARING THE COMMERCIAL LAUNCH FOR THE TRADING OF ANCILLARY SERVICES IN LUZON AND VISAYAS UNDER THE PHILIPPINE WHOLESALE ELECTRICITY SPOT MARKET WHEREAS, Section 37 of Republic Act No. 9136, otherwise known as the “Electric Power Industry Reform Act of 2001" or “EPIRA” mandates the Department of Energy (DOE) to ensure the reliability, quality, and security of supply of electric power, encourage power sector investments in the electricity sector and promote development of indigenous and renewable energy sources and develop policies and procedures and, as appropriate, promote a system of energy development incentives to enable and encourage electric power industry participants to provide adequate capacity to meet demand including, among others, reserve requirements: WHEREAS, the DOE is also mandated under Section 30 of the EPIRA to establish the Wholesale Electricity Spot Market (WESM) and upon joint endorsement with the electric power industry participants, formulate and promulgate tie WESM Rules: WHEREAS, on 28 June 2002, the WESM Rules was issued, adopted, and promulgated by the DOE: and pursuant to Section 10.3 (Transitory Provision) of the WESM Rules, only e 'py shall initially be traded; WHEREAS, Section 3.3.4.1 of the WESM Rules provides that when reasonably feasible, the Phitippine Electricity Market Corporation (PEMC) as the Market Operator, in coordination with the System Operator (SO), shall establish and administer a spot market for the purchase of certain reserve categories; WHEREAS, on 08 January 2007, the PEMC filed an application before the Energy Regulatory Commission (ERC) to secure the approval of the Pricing and Cost Recovery Mechanism (PCRM) for the WESM Reserve Market docketed as ERC Case No. 2007 — 004 RC (WESM Reserve PCRM Case) in compliance with the ERC Decision dated 20 June 2006 in ERC Case No. 2006-007 RC (WESM Price Determination Methodology) which provides that PEMC in coordination with SO shall establish and administer a spot market for purchase of certain reserve categories; WUEREAS, under the Philippine Grid Code (PGC), the National Grid Corporation of the Philippines (NGCP), as the SO of the nationwide transmission system, is responsible for determining, acquiring, and dispatching the capacity needed to supply the ancillary services required to maintain power quality and the reliability and security of the nationwide grid following the dispatch schedule prepared by the Market Operator: WHEREAS, the WESM Rules and the Order dated 07 July 2008 by the ERC in WESM Reserve Market PCRM Case, provided for the operation of the Reserve Market as a gross Energy Center, Merritt Rd., Fort Bonifacio, Taguig, Metro Manila, Philippines Tels: (Trunks) 840-1401 to 40; Fax 840-2067; 840-2236: 840-2067 (Domestic); 632-840-2173; 632-840-2236; 632-840-2067 (International) === dc2013-12-0027-pages-2.ppm === and undertake all necessary action to implement the Reserve Market on Commercial Launch [ate. PEMC shall, at least thirty (30) days before the Commercial Launch Date, submit to the DOE a cettification attesting that all systems and procedures, including all interfaces with the participants and service providers, necessary for the operation of the WESM Reserve Market are in place. The DOE shall confirm the Commercial Launch Date upon determination that the certification submitted by PEMC is acceptable. In the event that PEMC fails to certify readiness or the DOE finds PEMC’s certification deficient, PEMC or any relevant entity as may he determined by the DOE shall immediately rectify or remedy the deficiency. {n this ease. the DOE shall, in the exercise of its discretion, declare a new Commercial Launch Date. subject to receipt of a new certification from PEMC on the readiness of the Reserve Market. Section 3. Call for Registration. In preparation for the Commercial Launch Date, all Generation Companies or Customers intending to participate as Ancillary Service Provider in the WESM Reserve Market are directed to register with the Market Operator on a per generating unit basis or reserve facility. PEMC is hereby directed to provide the list of hecessary requirements for the concerned generators or Customers to be able to comply with this directive. Section 4, Responsibilities. Pursuant to their respective functions provided under the EPIRA and its Imptementing Rules and Regulations, the WESM Rules, the Philippine Grid Code, and all other relevant laws and issuances, the following agencies and entities are hereby directed to undertake the following: (a) Philippine Electricity Market Corporation (PEMC), i. Submit to DOE detailed report and status of the proposed WESM Reserve Market within fifteen (15) days from the effectivity of this Circular; ii. Undertake preparatory activities for the Commercial Launch Date including, but not limited to. the filing of the appropriate pleading/s with the ERC in order to implement the directives provided herein; iti, = Conduct the necessary trainings and other information dissemination activities lo ensure the readiness of participants including Generation Companies and Customers intending to participate in the WESM Reserve Market; iv. Regularly publish in the WESM Public Information Website the activities undertaken or activities to be undertaken relative to the developments for the commercial operations of the WESM Reserve Market: and v. Submit to DOE, on a regular basis. reports on the preparations and development on the WESM Reserve Market which shall be the basis for the readiness determination to pursue its commercial launch. Towards this end, all electric power industry participants and customers connected to the establishment of the WESM Reserve Market are directed to comply with the requirements of PEMC on the submission of information or === dc2013-12-0027-pages-3.ppm === t data necessary for the purpose of conducting simulations, assessing WESM Reserve Market readiness, or for such other purpose relevant to the commercial launch of the WESM Reserve Market. (b) National Grid Corporation of the Philippines (NGCP). i. Undertake activities to ensure that the performance of its functions and obligations on the provision of ancillary services are in compliance with the EPIRA and its Implementing Rules and Regulations, the WESM Rules, the Philippine Grid Code, the Open Access Transinission Services (OATS) Rules, and other relevant rules and regulatory issuances. ii. Collaborate with PEMC for the timely completion of the necessary enhancements to the WESM Dispatch Protocol and Ancillary Services Monitoring Manual. ensure the reliability of the Energy Management System (EMS) in the transmission of data to the Market Management System (MMS), implement necessary enhancements to the EMS-MMS Interface, and participate in the trainings and public dissemination organized by DOE and PEMC for the purpose of explaining matters relevant to the requirements of the SO for the various reserve categories, monitoring and compliance of reserve facilities, and such other matters within the competence of the SO; lit. Ensure that the testing and certification of all generating units capable of providing ancillary services. including customers intending to participate in the WESM Reserve Market, will be completed in accordance with the timeline set for the Cominercial Launch Date of the WESM Reserve Market. NGCP is hereby directed to provide the list of necessary requirements for the concerned ancillary services providers and customers to be able to comply with this directive: and iv. Regularly submit to DOF status report of its Ancillary Services contracts. (c) National Electrification Administration (NEA). As provided for in Section 3.3 of DOE Department Circular No. DC2010-06-007 and pursuant to its mandate under Republic Act No. 10531 or the NEA Reform Act, the NEA shall render appropriate assistance to Electric Cooperatives in ensuring their readiness for the commencement of the WESM Reserve Market. (d) All] WESM Members and Electric Power Industry Participants. Consistent with Section 3.4 of DOE Department Circular No. DC2010-06-007, all WESM members, as well as Generation Companies and customers intending to participate as Ancillary Service Provider in the WESM Reserve Market, are hereby directed to undertake all necessary preparations for the commencement of the WESM Reserve Market. including but not limited to compliance with applicable rules and regulations, and the requirements of the Market Operator and the SO. === dc2013-12-0027-pages-4.ppm === a f Pursuant to Section 4(b)(iii) of this Circular, all Generation Companies and/or plant operators are hereby directed to comply with the list of requirements issued by the NGCP to facilitate the timely testing and certifications of the generating units, in accordance with the timeline of the Commercial Launch of the WESM Reserve Market. Section 5. Must Offer of Capacities in Energy and Reserve. Upon the Commercial launch of the WESM Reserve Market and consistent with the WESM Rules 3.5.7.2 and 3.5.8.2. all Trading Participants are directed to submit offers for energy based on their Maximum Available Capacity and reserve based on their Maximum Capability for each trading interval. Por avoidance of doubt, “Maximum Available Capacity" shall have the same meaning as provided in Section 2.1 of DOE Department Circular No. DC2010-03-0003 while "Maximum Capability" shall refer to WESM Rule 3.5.7.3 (a). Section 6. Conduct of Trial Operations. Similar to the commencement of the commercial operations of the Luzon and Visayas energy only market, PEMC shall conduct trial operations of the WESM Reserve Market consistent with the existing protocols on the Reserve Market without any settlement. This is to adequately prepare the market participants in the trading of WESM reserve and allow final refinements when necessary prior to Commercial Launch Date. Section 7. Supervision by the DOE. The DOE. shall continue to oversee the WESM, including the Reserve Market. and to undertake such actions as may be necessary to achieve the objectives of the EPIRA and the WESM. Section 8. Regulatory Support. Consistent with its mandate to ensure competition in the generation and supply sectors, and in support of the provision of adequate, reliable and secured electricity services, the ERC shall render timely action on applications filed in relation to the operationalization of the WESM Reserve Market, particularly on the PCRM. Section 9. Reportorial Requirements. For purposes of monitoring compliance with the directives under this Circular, PEMC, NGCP, and NEA shall submit to the DOE monthly reports and issues register on the process and status of their preparations and readiness. Section 10. Interpretation. Words and meanings stated in this Circular shall have the same meaning in the WESM Rules. Section 11. Separability Clause. If for any reason, any section or provision of this Circular is declared unconstitutional ot invalid, such parts that are not affected shall remain in full force and effect. Section 12. Effectivity. This Circular shall take effect immediately following its publication in Wo (2) newspapers of general circulation and shall remain in effect unless otherwise revoked. PEMC is directed to publish this Circular in the market information website. Dove this day of November. 2013 at Taguig City, Metro Manila, Philippines. —_— CARLOY JERICHO L. PETILLA Secretary ‘DEPARTMENT OF ENERGY WA !N REPLYING PLS CITE: SOE-JLP-13006689 | er Ml DEC 02 2013