DC2021-06-0015
Full title: Guidelines on the WESM Central Scheduling in Mindanao
Issued: 18 June 2021 | By: DOE (6 pages)
Note — citation discrepancy:
wiki/pages/concepts/wesm.mdpreviously attributed the national five-minute trading interval change to DC2021-06-0015. The actual DC2021-06-0015 is the WCS operational guideline specific to the Mindanao pre-COD period (text confirmed from pdftotext). The five-minute dispatch national enhancement was a separate issuance.
Context
During the WESM Central Scheduling (WCS) period for Mindanao — before full commercial operation on 26 January 2023 (declared by DC2022-12-0039) — all Mindanao Generator Trading Participants were required to implement 5-minute dispatch schedules generated from the New Market Management System (MMS). Settlement during WCS remained based on existing bilateral contractual arrangements; there was no WESM financial settlement [DC2021-06-0015, §1 Background, 2021-06-18].
Key Provisions
Generator Responsibilities (§2.1)
- Maintain access to MMS Market Participant Interface (MPI) via Digital Certificate and valid credentials, or via API Web Service
- Communication protocol with plant operators for 5-minute dispatch coordination
- Report issues to Market Operator
- Submit working offers based on Day-Ahead Generation Schedule (DAGS): MW up to DAGS at PhP0.00/MWh; preferred price for MW beyond DAGS up to maximum available capacity
System Operator Responsibilities (§2.2)
- EMS available for MO real-time data capture via ICCP
- Submit input constraints (overriding constraints, outages, transmission limits, reserve requirements)
- Submit re-dispatch instructions to MO
Market Operator Responsibilities (§2.3)
- Regular regional demand forecasts for WAP, DAP, HAP, and RTD runs
- MMS and MPI always available
- Submit evaluation of WCS to DOE
Dispatch Procedures (§3)
- Scheduled generators submit standing offer profiles; Must-Dispatch/Priority Dispatch/Non-Scheduled submit standing nomination profiles
- Startup clearance request ≥4 hours before scheduled start
- Generators ramp to 5-minute RTD dispatch schedules (subject to SO re-dispatch for ancillary services or Load Adjustment Notices)
- 3 possible RTD below-Pmin conditions: (1) if online, ramp to Pmin; (2) if offline, stay offline; (3) if starting/stopping, ramp toward RTD
Settlement During WCS (§3.8)
- Settlement based on existing contracts between generators and customers in Mindanao
- No settlement of WESM transactions
Non-Compliance (§3.9)
- Non-compliant generators must report reasons to PEMC’s Enforcement and Compliance Office
- Reasons logged through Dispatch Conformance Display in MPI