PEP 2023-2050 Vol. III Section A: Philippine Nuclear Energy Program
Source: PEP 2023-2050 Vol. III, pp. 1–6 (PDF pp. 8–13)
Coverage
Section A describes the institutional structure, IAEA milestone roadmap, key accomplishments, and long-term targets of the Philippine Nuclear Energy Program.
Key Facts Extracted
- NEPIO established 2016 (DOE); NEP-IAC created by EO 116 (July 2020), DOE chairs, DOST vice-chairs, 24 member agencies, 6 SCs covering 19 IAEA Infrastructure Issues
- EO 164 (February 2022): issued National Position on nuclear
- 123 Agreement with the US signed November 2023 (San Francisco); 7-month negotiation; witnessed by President Marcos Jr.
- IAEA Milestone Approach: 3 milestones — foundational (2023–2024, complete), project development (2024–2028), construction (2028–2032)
- First commercial operation: 2032 at 1,200 MW; 2,400 MW by 2035; 4,800 MW by 2050
- 11 potential NPP sites assessed; Mindoro and Palawan flagged for SMR consideration
- SMRs highlighted as faster to deploy, off-grid potential
- Independent nuclear regulatory body targeted under Milestone 2
Pages Created/Updated
concepts/nuclear-energy-program.md— expanded with governance, milestones, 123 Agreement, SMR detailconcepts/ph-us-123-agreement.md— new pagemeta/entities.md— added IAEA, NEPIO, NEP-IAC