PDP 2023-2050 Ch.1 — Total Electrification, ER 1-94, EVOSS, Major Policies
Source: raw/_pdf/planning-docs/pdp-2023-2050.pdf, document pages 31–48 (PDF pages 31–48; offset 0).
Coverage
Pages 31–48 conclude Chapter 1 of the PDP 2023-2050. This section covers:
- Sections 7–7.4: Total electrification status and programs (grid and off-grid)
- Section 8: Overarching policies — EVOSS additional process flows
- Section 9: Major policy issuances Jan 2021 – Jun 2023 (65 policies, Table 23)
Key Findings
7.1 Total Household Electrification
2022 Status (DU-reported, 2015 PSA Census basis):
- National electrification rate: 96.2% (up from 95.4% in 2021)
- Served HHs: 25,914,073 of 22,984,971 potential HHs
- Unserved: 879,232 HHs
- By DU type: ECs 94.2%; MERALCO 100%; MGSP/QTP 62.6% (23,696 HHs)
Electrification hierarchy (least-cost): grid interconnection → microgrid → PV-SHS [PDP 2023-2050, p.31, 2025]
7.2 Grid Electrification Programs
NIHE (Nationwide Intensification of Household Electrification):
- 274,035 of 344,090 approved HHs energized in 2022
- COVID-19 halted installation for remaining beneficiaries; DOE drafting guidance Advisory [PDP 2023-2050, p.33, 2025]
SEP (Sitio Electrification Program):
- December 2022: 951 of 1,085 DBM-approved sitios energized under 2022 GAA
- Estimated project cost: PhP 1.27 billion [PDP 2023-2050, p.33, 2025]
BLEP (Barangay Line Enhancement Program):
- Converts off-grid barangays (gensets, SHS, micro-hydro) to grid connection
- 2022–2026 target: 166 barangays; proposed budget: PhP 2.4 billion (GAA, subject to NG subsidy) [PDP 2023-2050, p.33, 2025]
7.2.2 Off-Grid Programs
DOE PV Mainstreaming (LFP Component):
- Fee-for-Service model; ECs own and maintain hardware; HH responsible for wiring and DC loads
- Completed: 11,113 HHs across 7 EC projects (QUEZELCO II 1,333; BISELCO 3,711; BOHECO II 530; SULECO 2,575; ZAMSURECO I 1,129; ILECO II 706; BISELCO Batch 2 1,129)
- All projects endorsed to ERC per ERC Resolution No. 17 s.2017 [PDP 2023-2050, Table 17, 2025]
EU-ASEP PVM Component:
- Total: 40,500 HHs across 6 ECs
- Window 1 (10,000 HHs): LGUGC implementing; completed March 2019; EU + GPOBA financing; ECs: COTELCO, DASURECO, SOCOTECO II, SUKELCO
- Window 2 (30,500 HHs): NPC implementing; completed September 2022; EU financing; ECs: FIBECO, BUSECO, COTELCO, SUKELCO, DASURECO, SOCOTECO II [PDP 2023-2050, Table 18, 2025]
MGSP Operators (December 2022):
- 10 existing sites; 3 operators: PSPI (6 sites), SREC (1 site), FPIEC (3 sites)
- Former QTP operators transitioned to MGSP status June 2022 upon MGSA-IRR taking effect
- Site locations: Malapascua Cebu; Liminangcong/Candawaga/Cuyo/Port Barton/Balut (Palawan and Saranggani); Sitio Sabang Puerto Princesa (SREC); Lahuy/Haponan/Quinalasag Caramoan Camarines Sur (FPIEC)
- Technologies: PSPI mostly diesel-only; SREC hybrid diesel+solar 1.452 MWp+BESS 2.44 MWh; FPIEC hybrid solar+diesel+BESS [PDP 2023-2050, Table 19, 2025]
MCPHC/ARC Palawan Award:
- DOE PN2022-01-001 (05 Jan 2022): 39 PALECO areas declared open; PALECO CSP April 2022
- Notice of Award: 17 June 2022 to MCPHC in consortium with Clean Grid Partners Pte. Ltd. and WEnergy Global Pte. Ltd.; SPV = Archipelago Renewable Corporation (ARC)
- 12 lots in Dumaran, Bataraza, Quezon, Rizal, Taytay, San Vicente, and El Nido municipalities (all Palawan)
- All solar-diesel-BESS hybrids [PDP 2023-2050, Table 20, 2025]
7.3 ER 1-94 Fund Status
As of December 2022: PhP 5.055B disbursed (78.7%) of PhP 6.425B total; PhP 1.370B remaining. DC2020-04-0008 allowed EF funds to be used for COVID-19 host LGU projects; DOE Advisory 08 May 2023 invoked Sunset Clause reverting EF back to electrification purpose [PDP 2023-2050, Table 21, 2025].
7.4 IP/ICC Extension
59 Host IPs/ICCs enlisted; 27 power generation facilities; 7 regions (CAR, II, III, V, VI, XI, XII). DC2018-03-0005 (recognition of rights); DC2019-06-0010 (administrative operating guidelines). Coordinated with NCIP for direct remittance [PDP 2023-2050, p.42, 2025].
8. EVOSS Additional Process Flows
EVOSS established by RA 11234 (08 March 2019). EPIMB administered 885 endorsements/approvals Aug 2020–Dec 2022 (Table 22). Four new process flows added 2021–2022 (Q1 2023 EVOSS integration target):
- Letter of Endorsement to DAR for Land Use Conversion
- SIS Exemption for projects <20 MW (Luzon) / <5 MW (Visayas/Mindanao)
- Certificate of Endorsement for P2P Limited Transmission Facilities
- Certificate of Endorsement to ERC for MGSP [PDP 2023-2050, p.43, 2025]
9. Major Policy Issuances (January 2021 – June 2023)
65 policies issued across 9 subsectors. Notable policies not yet fully represented in wiki:
- DO2023-05-0015 (23 May 2023) — LNG non-discriminatory treatment enjoining ERC and others
- DO2023-06-0018 (08 Jun 2023) — Creating PAAT-TNPSO (Performance Assessment Audit Team for NGCP)
- DC2021-03-0003 (02 Mar 2021) — DDP formulation guidelines for DUs
- DC2022-05-0014 (10 May 2022) — Amending DC2020-01-0001 on direct connection applications
- DC2022-12-0038 (23 Dec 2022) — Declaring WESM commercial operation in Mindanao Grid
WESM-related amendments (47 of 65 policies) cover reserve market implementation, enhanced WESM design, billing/settlement, and metering — already tracked in Wholesale Electricity Spot Market (WESM) .
Pages Created or Updated
| Page | Action |
|---|---|
| National Total Electrification Roadmap (NTER) 2023-2032 | Added NIHE section; added BLEP section; expanded PV-SHS with DOE-LFP EC table (Table 17) and EU-ASEP Windows 1 & 2 (Table 18); added PDP source |
| Microgrid Policy and Off-Grid Electrification | Added existing MGSP operators table (Table 19); added MCPHC/ARC Palawan award (Table 20); added new entities to frontmatter |
| Energy Regulations 1-94 (ER 1-94) | Added fund status Dec 2022 (Table 21); added COVID-19 DC2020-04-0008; added IP/ICC extension (DC2018-03-0005, DC2019-06-0010) |
| Energy Virtual One-Stop Shop (EVOSS) | Added RA 11234 legal basis; added EPIMB issuances table (Table 22); added 4 new process flows |
Raw extraction: pdftotext output