NREP 2020-2040 §B — 2020-2040 Targets and RE Outlook

Source: raw/_pdf/planning-docs/nrep-2020-2040.pdf Chapter: Chapter II (NREP 2020-2040 Targets and Outlook) Pages: pp. 14–24 (PDF pp. 27–37; offset = 13)

Scope

Chapter II — the updated RE-share targets and five overarching goals, the PLEXOS-modeled RE Outlook 2021-2040 (new-build and generation-mix projections), and the committed/indicative RE project pipeline as of December 2021.


A. RE Targets and Goals

YearRE Share Target
2030At least 35%
2040At least 50%

Note: The 2030 target aims to revert RE share to its 2008 level when the RE Act was enacted — not to surpass historic highs.

Five overarching RE goals [NREP 2020-2040, p.15, 2022]:

  1. Energy Security — reduce dependence on imported fossil fuels; reduce exposure to price/exchange rate volatility
  2. Sustainable Development — aligned with AmBisyon 2040, Philippine Development Plan 2017-2022, SDG 7
  3. Climate Change Mitigation — NDC submitted 15 April 2021: 75% GHG reduction vs. BAU by 2030; energy sector = 59% of GHG (2019)
  4. Capacity Building — advances technical knowledge, R&D, distributed generation, storage, smart grid
  5. Inclusive Growth — RE/hybrid for off-grid areas; local investments; job creation

B. RE Outlook 2021-2040 — Modeling

Modeled using PLEXOS® (Energy Exemplar). Note: BESS, nuclear, hydrogen, fuel cell, ocean, and offshore wind were NOT included as new build options — these were categorized as emerging/experimental technologies at the time of model development [NREP 2020-2040, Table 3, p.17, 2022].

Table 5 — Philippines RE Outlook 2021-2040 (Cumulative New Build, in MW) [NREP 2020-2040, Table 5, p.20, 2022]:

Category20212025203020352040
Committed — Coal1,3002,9552,9552,9552,955
Committed — Natural Gas03,4043,4043,4043,404
Committed — Biomass1616161616
Committed — Geothermal2060140140140
Committed — Solar286409409409409
Committed — Hydro70144144144144
Committed — Wind132132132132132
New Build — Natural Gas07592,2598,15918,859
New Build — Solar02,6605,5858,91027,162
New Build — Hydro0002,2006,150
New Build — Geothermal008501,9002,500
New Build — Wind006,45013,05016,650
New Build — Biomass0120120360364
Existing Capacity22,95422,95422,95422,95422,954
Peak Demand16,48221,01929,12840,20954,655

Total installed by 2040: ~102,231 MW

Table 6 — Power Generation Mix (GWh and %) [NREP 2020-2040, Table 6, p.21, 2022]:

Plant Type2021 GWh2025 GWh2030 GWh2035 GWh2040 GWh
Coal64,70483,69684,30689,30384,491
Oil-based84140308509365
Natural Gas18,77613,81036,61858,10589,866
RE Total22,91737,07165,316109,384174,783
— Biomass8471,4551,4552,3312,353
— Geothermal9,57316,88323,29331,14435,321
— Solar1,2635,94510,43615,54043,686
— Hydro10,42411,67712,88426,04149,697
— Wind8101,11217,25034,32843,726
Total106,481134,717186,547257,301349,505
RE % Share22%28%35%43%50%
Coal %61%62%45%35%24%
Gas %18%10%20%23%26%

Key pattern: coal share actually grows in absolute GWh through 2035 before declining; natural gas plays a significant bridging role (18,859 MW new build by 2040 = largest single new-build category).

C. Upcoming RE Projects (as of Dec 2021)

Committed RE (901 MW, operational 2022-2027):

  • Solar: 489 MW (54%)
  • Hydro: 232 MW (26%)
  • Geothermal: 116 MW (13%)
  • Biomass: 65 MW (7%)
  • By grid: Luzon 694 MW (77%), Mindanao 114 MW (13%), Visayas 94 MW (10%)

Indicative RE (27,334 MW, potential operational 2022-2032):

  • Solar: 14,688 MW (54%)
  • Wind: 6,473 MW (24%)
  • Hydro: 5,862 MW (21%)
  • Geothermal: 274 MW (1%)
  • Biomass: 37 MW (<1%)
  • By grid: Luzon 22,789 MW (83%), Visayas 3,595 MW (13%), Mindanao 951 MW (3%)

[NREP 2020-2040, pp.22-24, 2022]