NREP 2020-2040 §A — NREP 2011-2030 Assessment

Source: raw/_pdf/planning-docs/nrep-2020-2040.pdf Chapter: Foreword/Executive Summary + Chapter I (NREP 2011-2030 Assessment) Pages: pp. xiii–13 (PDF pp. 13–26; offset = 13)

Scope

The document’s formulation context and Chapter I — a retrospective assessment of the previous NREP (2011-2030): installation outcomes vs. targets, the policy/program instruments deployed, and the six structural barriers that held back RE development.


Executive Summary

The NREP 2020-2040 was formulated by the DOE in collaboration with the National Renewable Energy Board (NREB) with technical assistance from the DREAMS Project (Development for Renewable Energy Applications Mainstreaming and Market Sustainability) — funded by the Global Environment Facility (GEF) and UNDP. A national public consultation was held on 18 March 2021 with 400+ stakeholder participants.

The document is anchored on AmBisyon Natin 2040 and aligned with the then-current PEP 2020-2040 and PDP 2020-2040 [NREP 2020-2040, p. xiii, 2022].


Chapter I — NREP 2011-2030 Assessment

A. Key Outcomes

Table 1 — NREP 2011-2030 Installation Targets vs. Actual, in MW [NREP 2020-2040, Table 1, p.1, 2022]:

Technology2010 BaselineTarget Addition (2011-2030)2030 TargetActual Addition (2011-2019)Actual Installed (Dec 2019)
Biomass39277316470363
Geothermal1,9661,4953,461831,928
Solar1284285958921
Hydropower3,4005,3948,7941953,760
Wind332,3452,378410427
Ocean0717100
Total5,4389,86515,3042,1157,399

Note: Totals may not sum due to rounding; differences between baseline+additions and actual reflect retirements or reclassifications.

Key findings:

  • 2019 actual (7,399 MW) = only ~48% of the 2030 target (15,304 MW)
  • Only solar and biomass exceeded their addition targets (solar: 958 MW vs. 284 MW target; biomass: 470 MW vs. 277 MW)
  • Geothermal added only 83 MW vs. 1,495 MW target — virtually no new development 2011-2019
  • RE share of power generation declined from 26% (2010) to 21% (2019) — coal grew from 34% to 55%
  • Despite shortfalls: PhP 217B RE investments (2009-2019), 168,400+ jobs created, 126.89 MW own-use RE facilities, 17.13M tons CO2 avoided [NREP 2020-2040, p.1-2, 2022]

B. Major Policies and Programs

Policy/ProgramKey CircularKey Detail
FiTERC Res 16 s.2010 (rules); ERC Res 10 s.2012 (initial rates); ERC Res 24 s.2013 (FIT-ALL guidelines)Solar target 50→500 MW; wind 200→400 MW; as of Dec 2021 only ROR hydro has 98.887 MW remaining; TRANSCO is FIT-ALL Fund Administrator (ERC Res 15 s.2012)
Net-MeteringERC Res 9 s.2013 (rules); ERC Res 6 s.2019 (amendments)2019 amendment: 20-day max for full interconnection process; removed Distribution Impact Study fee
Preferential DispatchDC2015-03-0001Wind/solar/ROR hydro/ocean = must dispatch; biomass under FiT = priority dispatch
RPS On-GridDC2017-12-0015MPs: DUs (captive), electricity suppliers (contestable market), gen cos (DCCs), others; 1% initial annual increment
RPS Off-GridDC2018-08-0024Aims to rationalize UC-ME and increase RE in off-grid areas; suspended and under review at time of NREP publication
GEOPDC2018-07-0019Voluntary; ≥100 kW average peak demand; non-regulated (direct contract with RE supplier)
RETFDO2018-10-0018 (23 Oct 2018)Special account in GFIs; 6 purposes per Section 28 RE Act
REMDC2019-12-0016 (4 Dec 2019)PREMS launched 17 December 2019; 1 REC = 1 MWh; RE Registrar operates the market
Omnibus GuidelinesDC2019-10-0013OCSP or direct application; Certificate of Registration for own-use projects
HEP55,248 households provided solar PV lighting (2010-2017)
RESHERRDC2012-11-009 (21 Nov 2012)RE Safety, Health, Environment Rules covering all RE technologies
CREZDC2018-09-0027 (18 Sep 2018)USAID/NREL support; identifies geographic zones with optimal RE resources

C. Issues and Challenges

Six structural barriers documented [NREP 2020-2040, pp.13, 2022]:

  1. Delayed policy implementation — RPS and GEOP issued years after RE Act (2008) mandated them
  2. Complex permitting — ~359 signatures from 74 agencies required for ROR hydro; ~1,340 days to complete
  3. Grid interconnection limits — existing grid unable to immediately absorb new RE; expansion projects delayed
  4. RE resource development — geothermal has 4-6 year gestation, 59% well success rate, no FiT; offshore wind/ocean lacking model projects
  5. Limited financing access — major banks favor large conglomerates; SME/IPP developers perceived as risky
  6. Climate risks — typhoon damage to RE plants; El Niño reduces hydro output