Ancillary Services (AS)

Ancillary services (AS) are services necessary to support the transmission of capacity and energy from resources to loads while maintaining reliable operation of the transmission system in accordance with good utility practice and the Philippine Grid Code [DC2021-10-0031, §3.1, 2021]. The System Operator (SO)NGCP — is responsible for procuring the required level and specifications of AS to maintain grid frequency, voltage stability, and fault recovery capability [DC2019-12-0018, §4, 2019].

AS Types

The Philippine grid recognizes five categories of ancillary service [DC2021-10-0031, Annex A §1.1, 2021]:

TypeAbbreviationFunction
Regulating ReserveRRAutomatic frequency control; continuous balancing of generation-load imbalance in real time
Contingency ReserveCRRapid response to sudden loss of a large generating unit or transmission element
Dispatchable ReserveDRSlower-responding backup capacity, deployed within minutes of dispatch instruction
Reactive Power SupportRPSVoltage regulation through supply or absorption of reactive power (VAR)
Black StartBSCapability to restart generation without external power supply following a system blackout

Note: “RPS” in this context denotes Reactive Power Support, not the Renewable Portfolio Standards program.

Required Reserve Levels

DC2019-12-0018 establishes per-grid AS quantity requirements per trading interval [DC2019-12-0018, §2.2, 2019]:

AS TypeRequired Level
Regulating Reserve4% of total demand
Contingency ReserveLargest synchronized generating unit, transmission element, or circuit interconnection import — whichever is greatest
Dispatchable ReserveSecond-largest synchronized generating unit, transmission element, or circuit interconnection import — whichever is greatest
Reactive Power SupportDetermined by SO via day-ahead load flow simulation
Black StartAt least 2 generating units contracted per power restoration highway; 1 must be available at all times

Capability testing thresholds: Mandatory AS capability testing applies to all generating units with Pmax at or above: Luzon ≥10 MW, Visayas ≥5 MW, Mindanao ≥5 MW [DC2019-12-0018, §3.1, 2019].

Ancillary Services Technical Working Group (AS-TWG)

DC2019-12-0018 created the AS-TWG to advise the DOE on AS policy development [DC2019-12-0018, §9, 2019].

Co-Chairs: DOE and ERC

Members (one representative each): ERC, DOE, NEA, NGCP, PEMC, IEMOP, Philippine Electric Power Operators Association (PEPOA), Manila Electric Company (MERALCO); plus three (3) representatives from the Philippine Independent Power Producers Association (PIPPA)

Secretariat: DOE Electric Power Industry Management Bureau (EPIMB)

The AS-TWG must convene within 30 days of the circular’s effectivity and submit its recommendations within 180 days, reviewed annually thereafter [DC2019-12-0018, §9.5, 2019]. The ERC must issue implementing rules within 60 days of receiving AS-TWG recommendations [DC2019-12-0018, §13, 2019].

Regulatory Framework

AS governance has evolved through a chain of department circulars:

InstrumentKey Content
DC2019-12-0018 (December 2019)General Framework for AS — mandates SO to procure full AS requirements; establishes required reserve levels (RR: 4% of demand; CR: largest unit; DR: second-largest); creates AS-TWG (DOE+ERC co-chairs); sets Reserve Market commercial operation target date (26 March 2020, subject to 6 readiness criteria); pre-Reserve Market: all 5 AS types via firm contracts only; post-Reserve Market: minimum contracted floors at 50% of RR/CR/DR requirements
DC2021-03-0009 (March 2021)Reserve Market Framework — mandates SO to procure AS through a combination of firm contracts and the co-optimized Reserve Market; directed competitive selection for contracts (superseded in part by DC2023-09-0026)
DC2021-10-0031 (October 2021)AS-CSP Policy — prescribes the competitive selection procedure for all AS contracts; establishes TPBAC; sets ASAPP annual planning cycle; includes ASPA TOR template
DC2023-09-0026 (September 2023)Reserve Market Commercial Operations — operationalizes the market-based reserve procurement channel; Phase 1 commenced 26 March 2024

See Reserve Market and Electricity Derivatives (WESM) for the co-optimized market channel. This page covers the contractual procurement channel governed by DC2021-10-0031.

Ancillary Service Agreement Procurement Plan (ASAPP)

The SO must submit an annual ASAPP to DOE by 31 March each year, and post it on its website by 30 April [DC2021-10-0031, §4.1–4.2, 2021]. The ASAPP contains [DC2021-10-0031, §4.3, 2021]:

  • AS types to be procured per grid (Luzon, Visayas, Mindanao)
  • Timing and monthly level of AS requirement per grid
  • Inventory of existing ASPAs (location, expiration dates)
  • 5-year historical hourly AS levels per type per grid
  • 10-year forward projection of AS requirements

The ASAPP serves as the basis for each CSP’s Terms of Reference, making it the primary planning instrument for AS procurement.

Third Party Bids and Awards Committee (TPBAC)

The SO procures AS through an independent TPBAC established by the NGCP Board of Directors [DC2021-10-0031, §5.1.1, 2021]. The TPBAC manages all CSP activities and is accountable for its decisions independently of the SO’s commercial interests.

Composition (5 voting members) [DC2021-10-0031, §5.1.2, 2021]:

SeatRepresentative
1SO officer with technical operations knowledge
2SO officer with competitive bidding/electricity pricing experience
3SO lawyer knowledgeable in transmission legal framework
4Market Operator (IEMOP) representative
5TransCo representative

The NGCP Board of Directors serves as observer only — it has no vote in TPBAC proceedings [DC2021-10-0031, §5.1.4, 2021]. This structural independence is the principal anti-capture mechanism. A quorum is a simple majority of voting members; decisions require majority of members present [DC2021-10-0031, §5.1.6–5.1.7, 2021].

The TPBAC is supported by a Technical Working Group (TWG) (technical, legal, and financial SO staff for ASAPP/TOR preparation, eligibility review, and bid evaluation) and a Secretariat (administrative support and keeper of CSP records) [DC2021-10-0031, §5.2, 2021].

Observers at all CSP stages: DOE, ERC, and NEA — invited in writing at least 7 working days in advance. Their absence does not nullify proceedings [DC2021-10-0031, §6.3–6.7, 2021].

Competitive Selection Process (AS-CSP)

Key CSP timelines [DC2021-10-0031, §7, 2021]:

StepDeadline
First CSP after effectivityWithin 6 months
Pre-bid conferenceWithin 14 days of ITB publication
Supplemental Bid Bulletin issuanceAt least 14 days before bid deadline
Total CSP duration (ITB to ASPA signing)90 calendar days
Joint ASPA filing with ERCWithin 15 working days of signing
Maximum ASPA term5 years

Prior to ITB publication, the SO must submit the TOR and draft Instruction to Bidders to DOE for approval [DC2021-10-0031, §7.4, 2021].

Bidder qualification rules [DC2021-10-0031, Annex A §13, 2021]:

  • ≤30% of installed generating capacity of any grid, and ≤25% of national installed generating capacity (EPIRA §45(a) caps)
  • SO affiliates are explicitly disqualified from participating
  • Affiliated bidders are not disqualified from competing against each other solely on that basis
  • For new ASPs: qualification based on personnel competence and operational management plan

Minimum unit size [DC2021-10-0031, Annex A §2.3, 2021]:

  • Luzon: 10 MW per AS unit (or aggregation)
  • Visayas: 5 MW
  • Mindanao: 5 MW

Reviewed annually; an AS unit may be a single generator or an aggregation.

Failed CSP: After two consecutive failed CSPs with no outstanding dispute, the SO may proceed to direct negotiation [DC2021-10-0031, §8.1, 2021]. A CSP is failed if: (a) no proposal is received; (b) only one bidder submits an offer (for RR, CR, or DR types); or (c) competitive offers do not meet TOR requirements [DC2021-10-0031, §8.2, 2021].

Payment Structure (ASPA Template)

AS contracts use a two-part payment structure [DC2021-10-0031, Annex A §3, 2021]:

1. Capacity Payment (PhP/kW/h) — paid for contracted capacity made available, regardless of dispatch. Compensates the provider for holding capacity on reserve.

2. Incidental Energy Payment (IE) — paid for energy actually dispatched, composed of:

  • Fixed Energy Fee (PhP/kWh)
  • Indexed Energy Fee (PhP/kWh, based on indices such as CPI or fuel prices)
  • Gross pumping/charging costs (for Energy Storage Systems)

AS dispatch is recovered primarily from WESM revenue. An IE surplus/shortfall mechanism adjusts the final payment [DC2021-10-0031, Annex A §3.2, 2021]:

IE surplus/shortfall = Σ G × ([IE payment offer + Capacity payment offer] − Actual WESM Price)

  • If positive (WESM price below AS payment offer): SO pays the shortfall to the AS provider
  • If negative (WESM price above AS payment offer): surplus offsets the IE payment to the provider in the next billing period

For Mindanao (pre-WESM establishment): Full AS Payment is paid directly by the SO to the AS provider monthly [DC2021-10-0031, Annex A §3.3, 2021].

Outage allowances [DC2021-10-0031, Annex A §6, 2021]:

  • Scheduled outage: 30 equivalent days per year
  • Forced outage: 15 equivalent days per year
  • No carry-over of unused allowance between years

For forced outages beyond allowance, the AS provider must procure replacement reserves from the Reserve Market or from other certified ASPs at ERC-approved rates; failure to do so triggers a penalty of half the Capacity Payment for the missed obligation period [DC2021-10-0031, Annex A §7.1(b), 2021].

Relationship to Reserve Market

The Philippines uses two parallel channels for AS procurement:

ChannelInstrumentMechanism
Firm contractsDC2021-10-0031 (AS-CSP)Multi-year bilateral ASPAs procured via competitive bidding; provides long-term supply certainty
Reserve MarketDC2023-09-0026Co-optimized dispatch in WESM; day-ahead/real-time market pricing; commenced Phase 1 commercial ops 26 March 2024

DC2021-03-0009 (2021) directed the SO to use a combination of both channels. The AS-CSP contract channel provides baseline certainty; the Reserve Market handles residual and real-time requirements. See Reserve Market and Electricity Derivatives (WESM) .

Protest Mechanism

Decisions of the TPBAC at any stage may be challenged in a two-step process [DC2021-10-0031, §10, 2021]:

  1. Reconsideration request to TPBAC — filed within 3 calendar days of notice; TPBAC resolves within 7 calendar days
  2. Protest to NGCP BOD — filed within 7 calendar days of reconsideration denial; BOD resolves within 7 calendar days; BOD decision is final

Court action (Rule 65) is available only after BOD finality. No protest stays the CSP proceedings; protests must be resolved before award [DC2021-10-0031, §10.4, 2021].

First AS-CSP Results

Under DC2021-10-0031, the SO conducted its first AS-CSP within the 6-month transitional period. 38 bidders received Notices of Award; 36 ASPAs were executed (2 bidders declined) [PDP 2023-2050, Ch.3 Sec.2.6, pp.107–108, 2025].